GAP concrete slab mounting
Chapter 5: Outdoor GAP Hardware Installation
GAP concrete slab mounting
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
■
This section shows the typical mounting used on a concrete slab for the outdoor GAP cabinet(s).
This section also applies to mounting the cabinets on a concrete floor as well.
Installation Planning
Since customer site configurations vary, the mounting of the GAP cabinet on a concrete slab will
vary. The installation needs careful planning before installing the GAP cabinet(s). Customer site
physical dimensions, cabinet ventilation, adequate air space around the equipment, minimum
cabinet door clearance and power routing all contribute to how to plan out the installation. For
utility mains power (AC power), local and country electrical code rules must also be taken into
consideration when planning the installation.
Concrete slab congurations
For a single cabinet, a 5 ft by 7 ft concrete slab is required. This also is the basic footprint of the
door clearance needed around the GAP cabinet, when the cabinet is mounted in the center of
the concrete pad as viewed from the top of the GAP cabinet.
5-4
68P09286A73-1
PRELIMINARY - UNDER DEVELOPMENT
JUL 2007
Содержание MOTOwi4 25600
Страница 9: ...List of Figures vi 68P09286A73 1 PRELIMINARY UNDER DEVELOPMENT JUL 2007 ...
Страница 11: ...List of Tables viii 68P09286A73 1 PRELIMINARY UNDER DEVELOPMENT JUL 2007 ...
Страница 27: ...FCC requirements 16 68P09286A73 1 PRELIMINARY UNDER DEVELOPMENT JUL 2007 ...
Страница 28: ...Chapter 1 Overview 68P09286A73 1 1 1 JUL 2007 PRELIMINARY UNDER DEVELOPMENT ...
Страница 49: ...Unpacking Chapter 2 Site Preparation 2 14 68P09286A73 1 PRELIMINARY UNDER DEVELOPMENT JUL 2007 ...
Страница 57: ...Cable Lengths Chapter 3 Cable Descriptions 3 8 68P09286A73 1 PRELIMINARY UNDER DEVELOPMENT JUL 2007 ...
Страница 84: ...Chapter 6 Optional Equipment 68P09286A73 1 6 1 JUL 2007 PRELIMINARY UNDER DEVELOPMENT ...
Страница 85: ...GAP Cabinet cabling Chapter 6 Optional Equipment 6 2 68P09286A73 1 PRELIMINARY UNDER DEVELOPMENT JUL 2007 ...
Страница 86: ...Chapter 7 What s Next and Cleanup 68P09286A73 1 7 1 JUL 2007 PRELIMINARY UNDER DEVELOPMENT ...
Страница 94: ...Chapter 8 XXXXXXXXXXXX 68P09286A73 1 8 1 JUL 2007 PRELIMINARY UNDER DEVELOPMENT ...
Страница 95: ...Installation checklist Chapter 8 XXXXXXXXXXXX 8 2 68P09286A73 1 PRELIMINARY UNDER DEVELOPMENT JUL 2007 ...
Страница 96: ...Chapter 9 XXXXXXXXXXXX 68P09286A73 1 9 1 JUL 2007 PRELIMINARY UNDER DEVELOPMENT ...
Страница 97: ...Installation checklist Chapter 9 XXXXXXXXXXXX 9 2 68P09286A73 1 PRELIMINARY UNDER DEVELOPMENT JUL 2007 ...
Страница 98: ...Chapter 10 XXXXXXXXXXXX 68P09286A73 1 10 1 JUL 2007 PRELIMINARY UNDER DEVELOPMENT ...
Страница 99: ...Installation checklist Chapter 10 XXXXXXXXXXXX 10 2 68P09286A73 1 PRELIMINARY UNDER DEVELOPMENT JUL 2007 ...
Страница 100: ...Chapter 11 XXXXXXXXXXXX 68P09286A73 1 11 1 JUL 2007 PRELIMINARY UNDER DEVELOPMENT ...
Страница 101: ...Installation checklist Chapter 11 XXXXXXXXXXXX 11 2 68P09286A73 1 PRELIMINARY UNDER DEVELOPMENT JUL 2007 ...
Страница 102: ...Appendix A Alternate RF Head Installation Procedure 68P09286A73 1 A 1 JUL 2007 PRELIMINARY UNDER DEVELOPMENT ...
Страница 103: ...A 2 68P09286A73 1 PRELIMINARY UNDER DEVELOPMENT JUL 2007 ...
Страница 104: ...Appendix B Alternate RGPS Installation 68P09286A73 1 B 1 JUL 2007 PRELIMINARY UNDER DEVELOPMENT ...
Страница 105: ...B 2 68P09286A73 1 PRELIMINARY UNDER DEVELOPMENT JUL 2007 ...
Страница 106: ...Appendix C MMI Cable Fabrication 68P09286A73 1 C 1 JUL 2007 PRELIMINARY UNDER DEVELOPMENT ...