7A
7B
02
EN
EN
03. CONFIGURATION
MENU EXTENSO 2
This test is performed before starting any operation. If it doesn’t detect security devices
connected in the CN3 06 output, the control board will reject opening/closing orders.
To enable the photocell test programming, read the following instructions:
01. Activate the extended menu 2 (see ACCESSING EXTENDED MENU 2 on page 6B).
02. Press SEL button and the CODE PED LED will begin to flash.
03. Press the SET button and the CODE PED LED will light up permanently, indicating
the programming’s success.
Repeat the operation to restore the previous configuration.
Change the operating mode of the PUL and BL inputs:
01. Activate the extended menu 2 (see ACCESSING EXTENDED MENU 2 on page 6B).
02. Press SEL button and the T. MOT LED will begin to flash.
03. Press the SET button and the T. MOT LED will light up permanently, indicating the
programming’s success.
Repeat the operation to restore the previous configuration.
Therefore, the PUL (CN3 → 3) input allows the connection of a push button (NO) to con-
trol only the opening and the BL (CN3 → 4) input allows the connection of a push button
(NO) to control only the closure.
• CODE PED |
PHOTOCELLS TEST
• T. MOT. |
PUL = OPEN | BL = CLOSE FUNCTION
RESET: If you need to restore the control board to the factory settings, press the SEL
and
SET keys simultaneously. At this time, all LEDs will light up simultaneously and
then will turn off, indicating the reset’s sucess.
04. COMPONENTS TEST
SCHEME FOR CAPACITATOR
To detect which components have problems in an electromechanical barrier installa-
tion, sometimes is necessary to conduct tests with a direct connection to a 110V or
230V power supply. For it is necessary to connect capacitor between the automation
and the power supply in order to test.
In the scheme below it is shown how this connection should be done and how the dif-
ferent component wires should be connected.
NOTES:
• To perform the test it is not needed to remove the automatism from the instalation,
because in this way it’s easier to understand if the automatism connected directly to
the power supply can function correctly;
• The linking order between the capacitator and the automatism wires is not impor-
tant, as long as it is connected, one with the brown wire and the other with the black
wire;
• The common wire must always be connected to the power supply.
• To reverse the automatism operating direction just swap the automatism black
wire with brown wire in the power supply direct’s connection.
This test only applies to a 110V or 230V barrier. To test a 24V barrier, simply connect
the motor wires to a 24V battery.
Black
Common (Blue)
BARRIER
Brown
CAPACITOR
10µF(230V)/20µF(110V)
POWER SUPPLY
110V or 230V