www.m o p e c .c o m
(800) 362- 8491
info @ m o p e c .c o m
Installation
1.
Locate package of smaller items (dissection board, tissue boxes, duct hose or filters)
When removing from the shipping platform, be careful if the unit has a foot pedal. The unit
should be removed from the shipping platform as to not cause damage to the plumbing
attached to the foot pedal.
2.
Leveling and Setting Unit in Place
This unit should be off the floor and resting on the leveling pads. The unit should be leveled to
ensure proper drainage. This allows water to evaporate or dry in case of a leak without getting
trapped by the base of the unit. Ensure there is a minimum of 2" from the wall to the back of
the unit. This allows for elevating units to move freely without any obstructions to the wall.
3.
Utility Connection
The only connections necessary are the Electric, Cold and Hot water supply, the drain
connection and the HVAC connections if in house ventilation. The disposal will need to be
installed prior to the electrical hook up. The unit is already pre wired and plumbed for the
options ordered.
4.
Electrical Connection
All electrical, water and ventilation stubs should be prepared in accordance with our rough-in
dimensions shown on rough in diagram of this manual.
The electrical service provided for the Maestro must include.
a. A switch or circuit breaker to which the wiring harnesses from the workstation will be
connected.
b. If plug and cord option is ordered NEMA L14-20R Receptacle.
Remove the access panels (see photo on next page if necessary). Elevate the unit to its
maximum upper position using the touch-screen. Install the disposal and make all
connections that apply. Reattach the access panels.
Each Maestro has a three foot whip for attachment to the facility, unless a plug and cord
are requested. The whip leads are labeled.