B-31
INST
ALLA
TION PROCEDURE
600
o
600
CEILING
CASSETTE
CEILING CASSETTE
S series
6. Drainage piping work
1. Connect the drain socket (supplied with the unit) to the drain port. (Fig. 6-2)
(Affix the tube using PVC adhesive then secure it with a band.)
2. Install a locally purchased drain pipe (PVC pipe, O.D. ø32).
(Affix the pipe using PVC adhesive then secure it with a band.)
3. Insulate the tube and pipe. (PVC pipe, O.D. ø32 and socket)
4. Check that drain flows smoothly.
5. Insulate the drain port with insulating material, then secure the material with a
band. (Both insulating material and band are supplied with the unit.)
Main unit
Insulating material
Band (large)
Drain port (transparent)
Insertion margin
Matching
Drain pipe (O.D. ø32 PVC TUBE)
Insulating material (purchased locally)
Transparent PVC pipe
O.D. ø32 PVC TUBE (Slope 1/100 or more)
Band (small)
Drain socket
Fig. 6-2
7. Electrical work
7.2. Indoor unit (Fig. 7-2) (Fig. 7-3)
Work procedure
1.Remove 2 screws to detach the electric component cover.
2.Route each cable through the wiring intake into the electric component box. (Pro-
cure power supply cable and indoor/outdoor connecting cable locally.)
3.Securely connect the power supply cable and the indoor/outdoor connecting cable
to the terminal blocks.
4.Secure the cables with clamps outside the electric component box.
5.Attach the electric component cover as it was.
• Fix power supply cable and indoor/outdoor connecting cable to electric component
box by using buffer bushing for tensile force. (PG connection or the like.)
Warning:
• Attach the electric component cover securely. If it is attached incorrectly, it
could result in a fire, electric shock due to dust, water, etc.
• Use the specified indoor/outdoor unit connecting cable to connect the in-
door and outdoor units and fix the cable to the terminal block securely so
that no stress is applied to the connecting section of the terminal block. In-
complete connection or fixing of the cable could result in a fire.
Fig. 7-2
7.1. Precautions (Fig. 7-1)
Electrical specification
Input capacity Main Switch/Fuse (A)
Power supply
SLZ-KA25
SLZ-KA35
SLZ-KA50
(1 phase ~/N, 230V,
50Hz)
10
10
20
• The compressor will not operate unless the power supply phase connection is cor-
rect.
• Grounding protection with a no-fuse breaker (earth leakage breaker [ELB]) is usu-
ally installed for
.
• The connection wiring between the outdoor and indoor units can be extended up to
a maximum of 50 meters.
A switch with at least 3 mm contact separation in each pole shall be provided by the
air conditioner installation.
*Label each breaker according to purpose (heater, unit etc.).
Fig. 7-1
Indoor unit
Outdoor unit
Wired remote controller
Wired main switch/fuse
Grounding
For Power supply
Electric component cover
Electric component box
Entry for Indoor-Outdoor connecting cable
Entry for wired remote controller cable
Cable clamp
Indoor/Outdoor unit connecting terminal
Wired remote controller terminal
(For SLZ-KA25/KA35/KA50VA)
Indoor controller
Power board
Earth cable
Fig. 7-3
11
30
30
30
,
(mm)
S3
S3
S2
S1
S2
S1
2
1
S1
S2
S3
1
2