4-1. PURGING PROCEDURES AND LEAK TEST

1) Remove service port cap of stop valve on the side of the outdoor unit gas pipe. 

(The stop valves are fully closed and covered in caps in their initial state.)

2) Connect gauge manifold valve and vacuum pump to service port of stop valve 

on the gas pipe side of the outdoor unit.

3) Run the vacuum pump. (Vacuumize for more than 15 minutes.)

4) Check the vacuum with gauge manifold valve, then close gauge manifold 

valve, and stop the vacuum pump.

5) Leave as it is for one or two minutes. Make sure the pointer of gauge manifold 

valve remains in the same position. Confirm that pressure gauge shows -0.101 

MPa [Gauge] (-760 mmHg).

6) Remove gauge manifold valve quickly from service port of stop valve.

7) Fully open all stop valves on the gas pipe and the liquid pipe. Operating without 

fully opening lowers the performance and this causes trouble.

8) Refer to 1-2., and charge the prescribed amount of refrigerant if needed. Be 

sure to charge slowly with liquid refrigerant. 

9) Tighten cap of service port to obtain the initial status.

10

) Leak test

Stop valve 

for GAS

Gauge mani-

fold valve (for 

R32, R410A)

Compound pressure 

gauge (for R32, R410A)

–0.101MPa 

 

(–760 mmHg)

Handle 

Low

Handle High

Vacuum pump

(for R32, R410A)

Charge hose  

(for R32, R410A)

*Close

*Open

Hexagonal 

wrench

*4 to 5 turns

Stop valve  

for LIQUID

Pressure gauge

(for R32, R410A)

Precautions when us-

ing the control valve

When attaching the control valve 

to the service port, valve core may 

deform or loosen if excess pres-

sure is applied. This may cause 

gas leak.

Service port

Charge hose 

(for R32, 

R410A)

Body

Close

Open

Control valve

A

When attaching the control valve to 

the service port, make sure that the 

valve core is in closed position, and 

then tighten part A. Do not tighten 

part A or turn the body when valve 

core is in open position.

4.  PURGING PROCEDURES, LEAK TEST, AND TEST RUN

Stop valve cap

(Torque 24.4 to 

30.4 N•m, 250 to 

310 kgf•cm

)

Service port cap

(Torque 10 to 12 N•m, 

100 to 120 kgf•cm

)

Service port cap

(Torque 10 to 12 N•m, 

100 to 120 kgf•cm

)

Stop valve cap

(Torque 21.5 to 

27.5 N•m, 220 

to 280 kgf•cm)

Make sure to replace the cap after 

the operation.

<R32>

4-2. GAS CHARGE

Perform gas charge to unit.

1) Connect gas cylinder to the service port of stop valve.

2) Perform air purge of the pipe (or hose) coming from refrigerant gas cylinder.

3) Replenish specified amount of the refrigerant, while operating the air condi

-

tioner for cooling.

Note:

In case of adding refrigerant, comply with the quantity specified for the refrig

-

erating cycle.

CAUTION:

When charging the refrigerant system with additional refrigerant, be sure to use 

liquid refrigerant. Charge the liquid refrigerant slowly, otherwise the compressor 

will be locked.

To maintain the high pressure of the gas cylinder, warm the gas cylinder with 

warm water (under 40°C) during cold season. But never use naked fire or steam.

Union

Stop valve

Liquid 

pipe

Indoor 

unit

Stop valve with 

service port

Gas 

pipe

Refrigerant gas 

cylinder  

operating valve

(for R32, 

R410A)

Gauge manifold 

valve (for R32, 

R410A)

Charge hose 

(for R32, 

R410A)

Refrigerant gas cylinder for R32, R410A 

with siphon

Electronic scale for refrigerant charging

Refrigerant (liquid)

Outdoor 

unit

Union

Union
Union

Make sure to indicate the followings with ineffaceable ink on the designated 

label / spec label.

(1) Precharged refrigerant amount – see spec label

(2) On site additionally charged amount

(3) Total refrigerant amount (1)+(2)

(4) (5) (6) CO

2

 equivalent

*1.  This information is based on Regulation (EU) No.517/2014.

*2.  According to IPCC 3rd edition, GWP is defined as 550.

(4) = (1) × 675/1000

(5) = (2) × 675/1000

(6) = (3) × 675/1000 

 WARNING

When opening or closing the valve 

below freezing temperatures, 

refrigerant may spurt out from the 

gap between the valve stem and the 

valve body, resulting in injuries.

Cap

Valve stem

Valve body

 WARNING

To avoid risk of fire, make sure that there are no flammable hazards or 

ignition risks before opening the stop valves.

VG79Y132H02_01En.indd   9

2020/01/31   11:45:28

Содержание MXZ-6F122VF

Страница 1: ...eve apenas a instalação da unidade exterior Quando proceder à instalação da unidade interior consulte o manual de instalação da unidade interior Installationshåndbog Til INSTALLATØREN Denne håndbog beskriver kun hvordan udendørsenheden installeres Vedrørende installation af indendørsenheden henvises til installationshåndbogen for indendørsenheden Installationsanvisning För INSTALLATÖREN Denna inst...

Страница 2: ...лі а потім мову BG Посетете горепосочения уебсайт за да изтеглите ръководства като изберете име на модел и след това език PL Odwiedź powyższą stronę internetową aby pobrać instrukcje wybierz nazwę modelu a następnie język CS Příručky naleznete ke stažení na internetové stránce zmíněné výše poté co zvolíte model a jazyk SK Na webovej stránke vyššie si môžete stiahnuť návody Vyberte názov modelu a z...

Страница 3: ...efrigerant circuit Any presence of foreign substance such as air can cause abnormal pressure rise and may result in explosion or injury The use of any refrigerant other than that specified for the system will cause mechanical failure system malfunction or unit breakdown In the worst case this could lead to a serious impediment to securing product safety Do not discharge the refrigerant into the at...

Страница 4: ...isk of combustible gas leakage When installing the unit be sure to secure the unit legs Where it is at least 3 m away from the antenna of TV set or radio Operation of the air conditioner may interfere with radio or TV reception in areas where reception is weak An amplifier may be required for the affected device Install the unit horizontally Please install it in an area not affected by snowfall or...

Страница 5: ...or more Blowing guide PAC SH96SG E Height of the obstacle is 1200 or less OK OK OK NG R32 is heavier than air as well as other refrigerants so tends to accumulate at the base in the vicinity of the floor If R32 accumulates around base it may reach a flammable concentration in case room is small To avoid ignition maintaining a safe work environment is required by ensuring appropriate ventilation If...

Страница 6: ...nt C Create an appropriate ventilation open area Make sure that the width of the open area is 0 9 m or more and the height of the open area is 0 15 m or more However the height from the bottom of the installation space to the bottom edge of the open area should be 0 125 m or less Open area should be 75 or more opening B Install in a space with a depression height of 0 125 m M kg Amin m 1 0 12 1 5 ...

Страница 7: ...ended cassette and ceiling concealed 2 2 m or more When installing floor standing refer to indoor unit Installation manual There are restrictions in installation height for each model so read the installation manual for the particular unit M kg Amin m 1 0 3 1 5 4 5 2 0 6 2 5 7 5 3 0 9 3 5 12 4 0 15 5 4 5 20 5 0 24 5 5 29 6 0 35 6 5 41 7 0 47 7 5 54 For wall mounted ceiling suspended cassette and c...

Страница 8: ...drain socket to one of the several drain holes Fix the drain socket into the drain hole of the base using the catches to secure it in place 4 Connect the soft PVC hose I D 15 mm as shown in the illustration 5 Make sure to provide drain piping with a downhill grade for easy drain flow 6 Glue the drain caps to close all the other unnecessary holes with the glue Prepare in the field Note Apply the gl...

Страница 9: ...ctly on the terminal block Be careful not to make mis wiring Fix the wire to the terminal block securely so that no part of its core is appeared and no external force is conveyed to the connecting section of the terminal block 3 Firmly tighten the terminal screws to prevent them from loosening After tightening pull the wires lightly to confirm that they do not move 4 Perform 2 and 3 for each indoo...

Страница 10: ...tion to prevent condensation Copper pipe 1 Cut the copper pipe correctly with pipe cutter Fig 1 2 2 Completely remove all burrs from the cut cross section of pipe Fig 3 Aim the copper pipe downward while removing burrs to prevent burrs from dropping in the pipe 3 Remove flare nuts attached to indoor and outdoor units then put them on pipe having completed burr removal Not possible to put them on a...

Страница 11: ...orque 24 4 to 30 4 N m 250 to 310 kgf cm Service port cap Torque 10 to 12 N m 100 to 120 kgf cm Service port cap Torque 10 to 12 N m 100 to 120 kgf cm Stop valve cap Torque 21 5 to 27 5 N m 220 to 280 kgf cm Make sure to replace the cap after the operation R32 4 2 GAS CHARGE Perform gas charge to unit 1 Connect gas cylinder to the service port of stop valve 2 Perform air purge of the pipe or hose ...

Страница 12: ...low 3 Turn on the main power for the air conditioner SW2 ON 1 2 3 4 5 6 20A ON 1 2 3 4 5 6 Factory setting Full SW1 ON 1 2 3 4 5 6 SW1 ON 1 2 3 4 5 6 SW1 ON 1 2 3 4 5 6 Lower the operating noise How to lower the operating noise 1 Be sure to turn off the main power for the air conditioner before making the setting 2 Set the 5 of SW1 on the outdoor controller board to ON to enable this function 3 Tu...

Страница 13: ... press the piping wiring correction switch SW871 again When the result is Not completed press the piping wiring correction switch SW871 again to cancel this function Then confirm the wiring and piping combination in a conventional manner by operating the indoor units one by one The operation is done while the power is supplied Make sure not to contact parts other than the switch including the P C ...

Страница 14: ...Information of spec name plate VG79Y132H02_backcover indd 1 2020 02 05 15 20 30 ...

Страница 15: ...m beskrivs nedan för användning i bostäder kommersiella miljöer och lätta industriella miljöer ev ticaret ve hafif sanayi ortamlarında kullanım amaçlı üretilen ve aşağıda açıklanan klima ve ısıtma pompalarıyla ilgili aşağıdaki hususları yalnızca kendi sorumluluğunda beyan eder декларира на своя собствена отговорност че климатиците и термопомпите описани по долу за употреба в жилищни търговски и ле...

Страница 16: ...zionale Colleoni Palazzo Sirio Ingresso 1 Viale Colleoni 7 20864 Agrate Brianza MB Italy Norwegian Branch Gneisveien 2D 1914 Ytre Enebakk Norway Portuguese Branch Avda do Forte 10 2799 514 Carnaxide Lisbon Portugal Spanish Branch Carretera de Rubi 76 80 Apdo 420 08173 Sant Cugat del Valles Barcelona Spain Scandinavian Branch Hammarbacken 14 P O Box 750 SE 19127 Sollentuna Sweden UK Branch Travelle...

Отзывы: