10. ELECTRICAL WORK
Hyper Heating Inverter R2-Series
The local standards and/or regulations is applicable at a higher priority.
10-4-2. PURY-HP144, 192, 240TSNU/YSNU
Power supply
Power supply
3-phase 3-wire
Note11,13
Note4
Note3
Note3
To *1 or *2
*1
Connector
CN41 CN40
Power supply
1-phase
208-230V 60Hz
Note11
Central control
transmission cable
>=1.25mm
2
Shield cable
(CVVS, CPEVS
MVVS)
Indoor-outdoor
transmission cable
>=1.25mm
2
Shield cable
(Using MA remote controller)
Connecting TB5 terminal.
G
G
TB7
(S)
TB7
(S)
TB1
(L1,L2,L3)
TB3
(M1,M2)
TB7
(M1,M2)
TB3
(M1,M2)
TB7
(M1,M2)
SC
Note12
OU
OU
Note4
To other OU
* Power supply
specifications vary with the
model of connected indoor
units or BC controller
<In the case a system controller is connected.>
TB1
(L1,L2,L3)
Note8
Power supply
1-phase
208-230V 60Hz
G
TB5
(M1,M2)
TB2
(L,N)
S
TB15
(1,2)
TB5
(M1,M2)
TB2
(L,N)
S
TB15
(1,2)
TB5
(M1,M2)
TB2
(L,N)
S
S
S
E
TB15
(1,2)
TB5
(M1,M2)
TB2
(L,N)
TB1
(R,S)
TB2 TB3
S
TB15
(1,2)
Transmission
booster
Note9
Note10
MA R/C
MA R/C
MA R/C
MA R/C cable
0.3-1.25mm
2
<=200m
Note5
IU
(Shield)
(Shield)
(Shield)
(Shield)
(Shield)
(Shield)
Note7
Note8
Pull box
*2
Indoor-outdoor
transmission cable
>=1.25mm
2
Shield cable
(Using ME remote controller)
Connecting TB5 terminal.
Power supply
1-phase
208-230V 60Hz
ME R/C
ME R/C
ME R/C
ME R/C cable
0.3~1.25mm
2
<=10m
Note5
Note7
Note8
Note8
Power supply
1-phase
208-230V 60Hz
Note11
G
TB5
(M1,M2)
TB2
(L,N)
S
TB15
(1,2)
TB5
(M1,M2)
TB2
(L,N)
S
TB15
(1,2)
TB5
(M1,M2)
TB2
(L,N)
S
S
S
E
TB15
(1,2)
TB5
(M1,M2)
TB2
(L,N)
TB1
(R,S)
TB2 TB3
S
TB15
(1,2)
Transmission
booster
Note9
Note10
IU
(Shield)
(Shield)
(Shield)
(Shield)
(Shield)
(Shield)
* Power supply
specifications vary with the
model of connected indoor
units or BC controller
Pull box
BC controller(Main)
TB02
(M1,M2)
S
(Shield)
BC controller(Sub)
TB02
(M1,M2)
S
BC controller(Main)
TB02
(M1,M2)
S
(Shield)
BC controller(Sub)
TB02
(M1,M2)
S
TB01
L,N
TB01
L,N
TB01
L,N
TB01
L,N
3-phase 3-wire
208-230V 60Hz(TNU)
460V 60Hz(YNU)
208-230V 60Hz(TNU)
460V 60Hz(YNU)
Note11, 13
G
G
G
G
Breakers for
current leakage Switch
Breakers for
current leakage Switch
Breakers for
current leakage Switch
Breakers for
current leakage Switch
Breakers for
current leakage Switch
Breakers for
current leakage Switch
Note:
1 The transmission cable is not-polarity double-wire.
2 Symbol means a screw terminal for wiring.
3 The shield wire of transmission cable should be connected to the grounding terminal at
Outdoor unit. All shield wire of M-Net transmission cable among Indoor units should be
connected to the S terminal at Indoor unit or all shield wire should be connected
together.
The broken line at the scheme means shield wire.
5 MA R/C transmission cable (0.3-1.25mm
2
) must be less than 200m in length, while ME
R/C transmission cable (0.3-1.25mm
2
) must be less than 10m in length. But transmission
cable to the ME R/C can be extend using a M-NET cable (>=1.25mm
2
) when the length
is counted in the M-Net length.
6 To wire PAC-YT53CRAU, use a wire with a diameter of 0.3mm
2
[AWG 22].
8 If using 1 or 2 (main/sub) MA remote controller to control more than 1 Indoor unit, use MA
transmission cable to connect all the TB15 terminals of the Indoor units. It is called
"Grouping".
If using 1 or 2 (main/sub) ME remote controller control more than 1 indoor unit, set
address to Indoor unit and ME remote controller. For the method, refer to 11-4. "Address
setting".
9 Indoor board consumes power from TB3. The power balance should be considered
according to System Design 11-3. "System configuration restrictions".
10 If Transmission booster is needed, be sure to connect the shield wires to the both sides
to the booster.
11 The critical current for choosing power source equipment is approximate
1.4 times of total rated current of the Outdoor unit(s) or Indoor unit(s).
12 When System controller (SC) is connected to the system, turn the SW5-1 on.
13 The phases of electricity power must be confirmed to be right used. Phase-reverse, or
phase-missing could break the controllers.
4 The connector change from CN41 to CN40 at one of the outdoor units will enable the
outdoor unit to supply power to TB7
. The transmission cable (above 1.25mm
2
, shielded,
CVVS/CPEVS/MVVS) among Outdoor units and system controllers is called central
control transmission cable. The shield wire of the central control transmission cable must
be grounded at the Outdoor unit whose CN41 is changed to CN40. When the power
supply unit PAC-SC51KUA is used, connect the shielded cable to the ground terminal on
the PAC-SC51KUA.
7 MA remote controller and ME remote controller should not be grouped together.
When a PAR-CT01MAU or PAR-40MAAU is connected to a group, no other MA
remote controllers can be connected to the same group.
230V
230V
PURY-HP72TNU
PURY-HP96TNU
PURY-HP120TNU
PURY-HP72YNU
PURY-HP96YNU
PURY-HP120YNU
Breaker for current leakage
460V
230V
208V
Model
Symbol
OU
IU
SC
MA R/C
ME R/C
Outdoor unit
60A 100mA 0.1sec. or less
70A 100mA 0.1sec. or less
70A 100mA 0.1sec. or less
50A 100mA 0.1sec. or less
60A 100mA 0.1sec. or less
60A 100mA 0.1sec. or less
25A 30mA or 100mA 0.1sec. or less
30A 30mA or 100mA 0.1sec. or less
35A 30mA or 100mA 0.1sec. or less
Indoor unit
System controller
MA remote controller
ME remote controller
21.2 (4)
21.2 (4)
21.2 (4)
13.3 (6)
21.2 (4)
21.2 (4)
Minimum Wire thickness
G wire
[mm
2
(AWG)]
Power wire
460V
208V
21.2 (4)
21.2 (4)
21.2 (4)
13.3 (6)
21.2 (4)
21.2 (4)
208V
[mm
2
(AWG)]
5.3 (10)
5.3 (10)
8.4 (8)
5.3 (10)
5.3 (10)
8.4 (8)