Commissioning & Starting the Shower
WARNING! For the Pumped low pressure valve you must follow the separate valve
commissioning sequence in the section below.
1
2
Turn on the electrical supply to digital mixing valve.
The digital mixing valve will power and perform a self check where the LED will indicate
a RED light initially and will then change to BLUE light after a few seconds.
Note: If the LED does not turn to a solid BLUE light after 10 seconds, indicating
the product is ready to use, refer to the troubleshooting or fault diagnosis section.
Turn on the water supply and open water inlet supply isolators.
Power Indication
LED