© MHG Heating Ltd
10
MHG Heating Ltd Unit 4 Epsom Downs Metro Centre, Waterfield, Tadworth, Surrey KT20 5LR
Telephone 01737 358000 Fax 08456 448803 Email
Web www.mhgheating.co.uk
010517
6.0 Electrical Connections
Basic electrical connection for all types of Wallcon
The wiring connections of the Wallcon boilers are located within two
terminal boxes mounted to the bottom of the boilers case.
All high voltage wiring is located in the left hand box and the low
voltage wiring in the right hand box.
All wiring via terminal blocks provided.
High voltage Wiring terminals
Power in to Boiler
230 Volts - 50 Hertz
Q2 Heating circuit pump
Live, Neutral, Earth, (Max switching 0.5Amp) (Q2)
Can be used as Multifunctional Output
Q3 Hot water charging pump
Live, Neutral, Earth, (Max switching 0.5Amp) (Q3)
Can be used as a Multifunctional Output
*Additional wiring to be added at commissioning if
required.
Additional outputs can be configured if required.
Low Voltage Wiring Terminals
Room Thermostat
Volt Free Enable, Not Polarity Sensitive, Room
stat/BMS ( <24 Volts) (H5)
0-10V enable *
Polarity sensitive, Max 10Volts, To be configured
at Commissioning, (H3)
Outside Air Temperature Sensor
QAC34 sensor provided for direct on boiler
weather compensation. (B9)
Cascade Sensor
QAD36 strap on sensor, provided on request.
Hot Water Enable
Thermostat or Sensor, to be configured at
commissioning, (B3)
Cascade Communication *
To be wired from Master boiler to all slave boilers
in parallel, polarity sensitive.
*Additional wiring to be added at commissioning if
required.
Additional outputs can be configured if required.
* Screened cable must be used for this connection.