Pre drill
hole
70mm
screw
P 4
Please retain product label and instructions for future reference
20
Step 1
Parts needed - No. 18 QTY 2
No. 19
QTY 2
No. 20 QTY 1
Lay the bearers (
No’s. 18, 19 &
20)
onto a firm and level
surface (
free from areas where
standing water can collect
) as
shown in the illustration.
Fix the framing together at
each corner using 2x70mm
screws, ensuring the frame is
flush.
*Ensure the 58mm side of the
bearer is laying on the base so
that you can screw the bearers
together on the 44mm side.
8x70mm Screws
18
19
19
Pre drill
hole
70mm
screw
Pre drill
hole
Step 2
Parts needed - No. 21 QTY 4
Place the small angled bearers
(
No. 21
) into each corner as
shown in the illustration.
*Ensure there is an equal
amount of space between each
frame.
Secure each of the frames in
place using 2x70mm screws
for each side of the bearer,
ensuring the framing remains
level.
8x70mm Screws
5
70mm
screw
Step 3
(See Pre-Assembly)
Parts needed - No. 5 QTY 2
No. 10 QTY 2
No. 11 QTY 1
Place the starter boards (
No’s.
5, 10 & 11
) on to assembled
base frame along the longest
sides.
*Ensure the notches at either
end of each board are flush
and level with the ends of the
frame.
Fix each of the starter boards
to the frame by screwing
through the notch into the
frame as shown in the
illustration.
4x70mm Screws
21
5
5
10
10
11
IMPORTANT:
Pre-drill before fixing screws.
18
Example picture
2 screws per bearer per end.