Installation manual
M-WRG-II M-U
2
- 39 -
Meltem Wärmerückgewinnung GmbH & Co. KG
Am Hartholz 4 · D-82239 Alling
[email protected] · www.meltem.com
VENTILATION THE RIGHT WAY
V E N T I L A T I O N & H E A T R E C O V E R Y
9
Installing the installation kit in a frame
construction
NOTICE
Frame constructions are implemented in many different ways, so it is not possible to
provide a generally-applicable description for every variant. This installation example
shows the installation in a frame construction with a framing member thickness of
160 mm. The installation will have to be adapted accordingly for other framing member
thicknesses or wall structures.
►
If you are in any doubt, please send us a dimension drawing of your wall section so
we can provide you with a custom solution.
9.1
Tools and equipment required
— Permanently elastic sealant, solvent-free if applied to polystyrene
— Sealing tape, 30 mm wide, e.g. Coroplast
— Sealing tape for bonding the wall box to the vapour barrier, e.g. Rissan
®
from SIGA
—
If necessary, wedges for fixing the wall box, 8x
alternatively use inflatable air cushions, 4x, e.g. Amo-Bag from Würth,
part no. 07156780
—
If necessary, wedges for fixing the filler piece, 4x
alternatively use inflatable air cushions, 2x, e.g. Amo-Bag from Würth,
part no. 07156780
— Adhesive tape
—
Expanding foam with abP (national technical test certificate of the DIBt) approval
(“exact gap” foam is recommended)
— Saw for cutting the ventilation pipes to length
— Saw for cutting the channels in the frame construction
— Styrofoam saw
— Spirit level