NBT40 SERVICE MANUAL BOOM
MAINTENANCE
cables (77) from anchor plate in the bottom base of the
5th stage boom and drape outside of base end of 3rd
stage boom.
33.
Disconnect lubrication tubes (194, 195) and pull the 5/4/
3 retract-2/3/4 extend pin (78) as an assembly out of slot
in the bottom base of the 4th stage boom and drape out
of the base of the 3rd stage boom. Remove and tag 5/4/
3 retract sheaves (79) and cables (77) from pin.
34.
Lower extend cylinder (6) to original position. Attach a
sling or chain to the tip of the 5th stage boom and pull
the 5th stage boom out of the 4th stage boom
approximately one foot. Remove the extend cylinder
from the boom, keeping the 2/3/4 extend cables (29)
taunt.
35.
Remove rods (153) and roller (165) and plate (166) from
cylinder sheave case tip. Remove sheaves (112) from
extend cylinder, if necessary by removing two
capscrews (109) and the keeper (115) from the sheave
pin (114) and lightly tapping the pin while removing the
sheaves from the tip of the extend cylinder.
36.
Remove wear pads (116,119) if replacement is
necessary.
37.
Remove the 2/3/4 extend cables (29) from the 5/4/3
retract-2/3/4 extend pin and store cables and extend
cylinder in an area where they will not be damaged
during further boom disassembly.
38.
Remove four nuts (86) which retain 3/4/5 extend cables
(96) to the top base end of the 3rd stage boom. Push 5th
stage boom back into 4th stage boom. Replace 5/4/3
retract-2/3/4 extend pin (78) back into slot in the bottom
base end of the 4th stage boom. Replace 5/4/3 retract
cables (77) into anchor plates at the bottom base end of
the 5th stage boom.
39.
Attach a sling or chain to the tip of the 4th stage boom
and pull (with the 5th stage boom) out approximately two
feet. Remove and tag upper side wear pads with shims
(94,93,92) and lower wear pads with shims (89,90,91)
and one top wear pad with shims (104,102,139,105)
from the tip of the 3rd stage boom.
40.
Remove four capscrews which retain the 5/4/3 retract
cable anchors (107) to the bottom tip of the 3rd stage
boom. Remove wear pads (187) from bottom tip of 3rd
stage boom. Pull the retract cable anchors out and keep
retract cables taunt while pulling 4th stage boom (with
5th stage boom) out of 3rd stage boom.
41.
Place the 4th and 5th stage booms on a suitable
horizontal surface.
NOTE:
Use caution not to pinch or crush retract cables
while lifting or supporting 4th stage boom.
42.
If necessary, tag and remove wear pads and shims from
the base of the 4th stage boom.
43.
Remove the 5/4/3 retract-2/3/4 extend pin (78) from the
bottom base of the 4th stage boom. Remove the 5/4/3
retract cables (77) from the anchor plates at the bottom
base of the 5th stage boom and store in an area where
they will not be damaged during further boom
disassembly.
44.
Attach a sling or chain to the tip of the 5th stage boom
and pull 5th stage boom out approximately six feet.
Remove and tag lower side wear pad with shims
(89,90,91) and two top wear pads with shims (94,93,92)
from the tip of the 4th section boom.
45.
Remove two allenhead capscrews, nuts and washers
from 3/4/5 extend cable wear pads (88) at base of 4th
stage boom and remove pads.
46.
Remove grease fittings (95) from 3/4/5 extend sheave
pin (189) at front tip of 4th stage boom. Remove ten
allenhead capscrews from 3/4/5 extend sheaves pin
(189) and remove from the 5th stage boom side plates
and out of machined spot faces. Remove 3/4/5 extend
sheaves (98).
47.
Remove wear pads (100) from the bottom tip of the 4th
stage boom. Pull the 5th stage boom out of the 4th stage
boom while keeping extend cables taunt.
48.
Place the 5th stage boom on a suitable horizontal
surface. Take care not to pinch or crush extend cables
while lifting or supporting 5th stage boom. If necessary
tag and remove wear pads and shims from the base of
the 5th stage boom.
49.
Remove 3/4/5 extend cables from the anchor plates at
the bottom base of the 5th stage boom and store in an
area where they will not be damaged during further
boom disassembly.
50.
Remove loadline sheaves (120) if desired, by removing
two capscrews, two lockwashers and the keeper (125)
from the sheave pins (164) and lightly tapping the pin
while removing sheaves and spacers until all sheaves
are removed from boom tip.
Additional Maintenance, Disassembled
Boom
1.
Clean all boom sections and inspect for wear, dents,
bent or crooked boom sections, gouged metal, broken
welds or any abnormal conditions. Repair or replace as
required.
2.
Inspect all sheaves for excessive groove wear or
abnormal rim wear. Replace as required.
3.
Inspect all sheave bearings for excessive wear or cut
inner liner material. If installed bearing diameter is
0.015 in larger than pin diameter, bearing must be
replaced. Any cut or gouge which causes the bearing
liner to lose strands is cause for bearing replacement.
Reference Only
Содержание National Crane NBT40 Series
Страница 1: ...Service Manual National Crane NBT40 Series R e f e r e n c e O n l y ...
Страница 2: ...R e f e r e n c e O n l y ...
Страница 122: ...BOOM MAINTENANCE NBT40 SERVICE MANUAL 4 48 Published 8 01 2017 Control 287 11 THIS PAGE BLANK R e f e r e n c e O n l y ...
Страница 136: ...HOIST NBT40 SERVICE MANUAL 5 14 Published 8 01 2017 Control 287 11 THIS PAGE BLANK R e f e r e n c e O n l y ...
Страница 162: ...OUTRIGGERS NBT40 SERVICE MANUAL 7 10 Published 8 01 2017 Control 287 11 THIS PAGE BLANK R e f e r e n c e O n l y ...
Страница 214: ...CRANE INSTALLATION NBT40 SERVICE MANUAL 9 36 Published 8 01 2017 Control 287 11 7488 4 7488 6 R e f e r e n c e O n l y ...
Страница 216: ...SCHEMATICS NBT40 SERVICE MANUAL 10 2 THIS PAGE BLANK R e f e r e n c e O n l y ...
Страница 218: ...NBT40 SERVICE MANUAL APL 2 THIS PAGE BLANK R e f e r e n c e O n l y ...
Страница 219: ...R e f e r e n c e O n l y ...
Страница 220: ...R e f e r e n c e O n l y ...