6-13
Published 11/26/2014, Control # 447-05
RT770E
SWING SYSTEM
6
GROVE
13.
Attach a suitable lifting device to the four superstructure
lifting lugs (two at the boom pivot shaft bushings and two
at the lower lift cylinder pivot shaft bushings). Take in
cable or chain to remove slack. Do not pull up on the
superstructure.
NOTE:
It will be necessary to rotate the superstructure
while attached to the lifting device. Outer race bolts
can only be removed from the front or from under
the cab.
14.
Remove the 40 bolts and washers securing the turntable
bearing outer race to the carrier.
15.
Carefully lift the superstructure, using care not to
damage the swivel assembly, and set it on blocking that
will not allow the superstructure to tilt or shift, or rest on
the swivel. Leave the lifting device attached.
NOTE:
If the same bearing is to be used again, mark the
position of the bearing on the superstructure so it
can be installed in the exact position before
removal.
NOTE:
The bearing weighs between 585 kg (1290 lb) and
642 kg (1415 lb) depending on the bearing used.
Ensure the bearing lifting device is capable of
supporting the weight.
16.
Place an adequate lifting device under the bearing and
remove the 44 bolts and washers securing the turntable
bearing to the superstructure.
17.
Using the lifting device, remove the turntable bearing
from under the superstructure.
Inspection
Check the bearing teeth for chipping or cracking. If any
evidence of these is found, replace the bearing. Ensure the
bolt holes are free of dirt, oil, or foreign material.
Installation
NOTE:
If the same bearing is to be used again, align the
marked teeth on the pinion shaft and the marked
teeth on the bearing.
Installation is in the travel position. Ensure the
swing lock is disengaged before attempting to mate
the bearing to the superstructure.
1.
Using an appropriate lifting device, position the turntable
bearing under the superstructure. If the same bearing is
being used, position it as marked prior to removal.
2.
Install 44 new bolts and washers securing the bearing to
the superstructure. Refer to Inner Race Torquing in this
Sub-Section.
3.
Using an appropriate lifting device, align the
superstructure over the carrier in the travel position and
carefully lower the superstructure, being careful not to
damage the swivel assembly, into position on the carrier
bearing plate.
NOTE:
It will be necessary to rotate the superstructure
while attached to the lifting device. Outer race bolts
can only be installed from the front or from under
the cab.
4.
Install 40 new bolts and washers. Refer to
NOTE:
If a new bearing is being installed, a new pinion
gear must also be used. Align the high point
(maximum eccentricity) on the bearing with the
new pinion gear high point.
WARNING
Ensure the superstructure is fully supported before
proceeding. Death or serious injury may result.
WARNING
Ensure that any blocking material used is capable of fully
supporting the weight of the superstructure and will not
allow it to tilt or shift. Failure to do so may result in death or
serious injury.
WARNING
Anytime a turntable bolt has been removed, it must be
replaced with a new grade 8 bolt. Death or serious injury
may result.
FIGURE 6-4
.
008 Thick
Shim By Full
Width To
Tooth
Engagement
(.016
Backlash)
Pinion
Max
Eccen-
tricity
Point
Содержание Grove RT770E
Страница 3: ...Service Maintenance Manual Grove RT770E ...
Страница 4: ......
Страница 40: ...INTRODUCTION RT770E SERVICE MANUAL 1 26 Published 11 26 2014 Control 447 05 THIS PAGE BLANK ...
Страница 124: ...HYDRAULIC SYSTEM RT770E 2 84 Published 11 26 2014 Control 447 05 THIS PAGE BLANK ...
Страница 126: ...ELECTRICAL SYSTEM RT770E SERVICE MANUAL 3 2 Published 11 26 2014 Control 447 05 FIGURE 3 1 7983 ...
Страница 149: ...4 5 Published 11 26 2014 Control 447 05 RT770E SERVICE MANUAL BOOM 4 GROVE FIGURE 4 2 ...
Страница 150: ...BOOM RT770E SERVICE MANUAL 4 6 Published 11 26 2014 Control 447 05 FIGURE 4 2 continued ...
Страница 151: ...4 7 Published 11 26 2014 Control 447 05 RT770E SERVICE MANUAL BOOM 4 GROVE FIGURE 4 2 continued ...
Страница 152: ...BOOM RT770E SERVICE MANUAL 4 8 Published 11 26 2014 Control 447 05 FIGURE 4 2 continued ...
Страница 153: ...4 9 Published 11 26 2014 Control 447 05 RT770E SERVICE MANUAL BOOM 4 GROVE FIGURE 4 2 continued ...
Страница 154: ...BOOM RT770E SERVICE MANUAL 4 10 Published 11 26 2014 Control 447 05 FIGURE 4 2 continued ...
Страница 224: ...5 24 Published 11 26 2014 Control 447 05 HOIST AND COUNTERWEIGHT RT770E This Page Blank ...
Страница 276: ...POWER TRAIN RT770E 7 30 Published 11 26 2014 Control 447 05 THIS PAGE BLANK ...
Страница 300: ...UNDERCARRIAGE RT770E 8 24 Published 11 26 2014 Control 447 05 FIGURE 8 28 ...
Страница 321: ...9 9 RT770E LUBRICATION 9 Published 11 26 2014 Control 447 05 GROVE 7114 17 1 4 2 7114 20 7114 10 3 FIGURE 9 1 ...
Страница 323: ...9 11 RT770E LUBRICATION 9 Published 11 26 2014 Control 447 05 GROVE 7114 17 11 12 7114 9 FIGURE 9 2 8130 1 ...
Страница 329: ...9 17 RT770E LUBRICATION 9 Published 11 26 2014 Control 447 05 GROVE 42 7114 25 7114 24 41a 7649 21 FIGURE 9 5 40 8130 2 ...
Страница 331: ...9 19 RT770E LUBRICATION 9 Published 11 26 2014 Control 447 05 GROVE FIGURE 9 6 8130 1 51 52 50 ...
Страница 336: ...LUBRICATION RT770E 9 24 Published 11 26 2014 Control 447 05 72 73 74 73 74 72 73 74 73 74 FIGURE 9 8 8133 ...
Страница 343: ...9 31 RT770E LUBRICATION 9 Published 11 26 2014 Control 447 05 GROVE 84 7114 30 FIGURE 9 11 85 7115 33 8130 2 ...
Страница 347: ...9 35 RT770E LUBRICATION 9 Published 11 26 2014 Control 447 05 GROVE 7649 22 101 100 FIGURE 9 13 8130 2 ...