MANDÍK CPV Installation, commissioning, and maintenance
IZU 02/2021
MANDÍK, a.s., www.mandik.cz
R
22
7.3
CONFIGURATION OF THE CONTROL SYSTEM FOR UNIT START-UP
The control system is completely installed from the factory and is pre-configured and tested for
the specific configuration of the unit.
During commissioning, it is critical to only control air output by changing the EC fan output
percentage and adjusting the schedule for the "Economy" / "Comfort" modes.
Fan output is set by default from the factory at the rated air output of the unit.
Make any changes to controller parameters as follows:
1)
using the cont
roller’s web interface and a laptop computer
to simplify the process of connecting the laptop to the controller, use the Ethernet port
located right next to the main switch
The IP address of the controller is 192.168.1.42
2)
using the integrated POL871 controller, if provided.
To change parameters and as a reference for the menu in the Siemens Climatix controller, use
the
“Detailed instructions for Climatix operation and commissioning”, available at:
https://mandik.cz/product-line/air-handling-units/control-system
in the Manuals and miscellaneous
section, and the Climatix operating instructions controls document.
8
COMMISSIONING
8.1
ACTIVITIES PRIOR TO INITIAL START-UP
The following must be performed prior to initial start-up:
•
activities prior to commissioning per the previous paragraph 6.
•
final technical audit of the electrical installation
•
adjustment of the fan speed per the values in the technical specifications of the unit