Chapter 9: Start-Up
36 | Installation, Operation & Maintenance Instructions EASYCHLORGEN
9. Start Up
Check
No.
SAFETY CHECK
Checked
(Yes / No)
1
Hydrogen gas detector fitted correctly at
high level in the EASYCHLORGEN
room.
2
EASYCHLORGEN
and Product Tank
ventilation is correctly installed to
external Zone 2 exhaust points
3
The EASYCHLORGEN mechanical
room has natural ventilation.
Note
Damage to the system due to incorrect
installation/commissioning.
Ensure essential commissioning checks are completed
correctly to avoid potential mechanical failure when
system placed into operation
Check
No.
PRE-START UP CHECK
Checked
(Yes / No)
4
PSU isolating transformer AC LINK wire
correctly configured to local voltage
conditions.
5
Suitable softened (minimum 3 bar
pressure) water supply available and
connected to EASYCHLORGEN.
6
Exposed DC copper busbar
connections are adequately protected
with self-amalgamating tape.
7
Saturator tank is supplied with softened
water supply.
8
Intermediate brine tank fitted where
necessary.
9.1 Commissioning and Initial Start-Up
Precondition for action:
The system is configured according to the factory setup.
The system has been installed in accordance with
section 7, Installation.
The softened water supply should be confirmed by
performing a water hardness YES/NO test. The sample
will be a GREEN result for soft water and RED result for
hard water. The result MUST BE GREEN, i.e. soft water.
DO NOT PROCEED further until a reliable softened
water supply is available.
The salt saturator is filled with a pre-charge of the correct
specification of salt and the water level has reached its
full level governed by the float valve. Saturation allowed
for at least one hour.
The hydrogen gas sensor detection kit is correctly
installed and electrically connected via the 4-pin
plug/M12 cable assembly as per installation instruction.
The PSU cabinet will require powering up to provide the
electrical supply to the whole system.
9.1.1 PSU Power Up
Perform the following working steps:-
1.
Switch on the PSU at the cabinet door main isolator.
2.
Disengage the Emergency Stop button by twisting and
pulling outward.
3.
The Power On (white) lamp will illuminate indicating that
there is power available to the system.
9.1.2 EASYCHLORGEN Control Panel Power Up
Perform the following working steps:
1.
Switch on the power supply to the EASYCHLORGEN at
the door main isolator. Next, the Start-up screen
appears:-
The EASYCHLORGEN system will perform a set
countdown number of water and brine batch cycles from
10 through to 0 (4250 model) or 15 through to 0 (8500
model) to initially charge the electrolyser with a minimum
WARNING
Risk of equipment failure and injury to personnel and
property!
Ensure the Pre-Start Up Check List is complete and all
instructions and installation criteria adhered to prior to
commissioning and start-up of the EASYCHLORGEN
system to avoid any immediate or ensuing risk.