Battery Installation
21
3.5
Battery Protection
3.5.1 Battery Undervoltage Pre-Warning
Before the end of discharge, the NX displays a battery undervoltage pre-warning. After this pre-warn-
ing, the battery has the capacity for 5 minutes discharging with full load (default time). The NX can
be user-configured to display this warning from 3 to 60 minutes before end-of-discharge.
3.5.2 Battery End-of-Discharge (EOD) Protection
If the battery voltage is lower than the end-of-discharge voltage, the battery converter will be shut
down.
3.5.3 Battery Fuse-Blow Warning
Battery current protection is provided by the battery fuses FU7 and FU8. If a battery fuse blows, the
NX displays the battery fuse-blow warning and the battery converter will be shut down.
3.6
External Battery Cabinet Installation
The following notes, in conjunction with the diagrams (
), illustrate the broad
principles to be followed when fitting and connecting the majority of battery cabinet installations.
When installing an external battery cabinet, the customer must provide overcurrent protection. See
for sizing of protection devices.
3.6.1 Fitting the Batteries
1. Leave at least 3/8 in. (10mm) on all vertical sides of the battery to permit free air circulation
around the batteries.
2. Allow adequate clearance between the top of the batteries and the underside of the shelf above for
monitoring and servicing the batteries.
3. When installing the batteries, always work from the bottom shelf up to prevent raising the center
of gravity, which could cause a tip-over hazard.
3.6.2 Connecting the Batteries
If the NX battery cabinets are installed on a raised floor, the battery power cables and circuit breaker
control cables may be routed to the UPS cabinet via the floor of the cabinet (bottom entry).
If the NX battery cabinets are installed adjacent to one another on a solid floor, these cables may be
passed between the cabinets through lifting slots in the lower sides of the cabinets.
Liebert recommends connecting the batteries in the following sequence:
1. Connect cables between batteries on each individual tray.
2. Attach cables connecting the battery trays
3. Connect the cables to the circuit breaker.
An insulating shroud should be fitted to each terminal after its connection has been made.
When connecting the cables between the batteries to the circuit breaker, always connect the circuit
breaker end of the cable first.
NOTE
All equipment servicing procedures must be carried out only by trained personnel.
NOTE
When using an external battery supply that is not provided with the UPS, please make
reference to the battery manufacturer’s installation manual for battery installation and
maintenance instructions, available on the manufacturer’s Web site. When replacing batteries,
Liebert recommends that the batteries in external cabinets be the same type used internally in
the NX. See
for a list of batteries that are approved for use with this product.
NOTE
If a battery breaker cabinet is not used, the customer must provided an isolating disconnect
device on the output of the battery cabinet.
Содержание NX 10kVA
Страница 1: ...POWER AVAILABILITY NX INSTALLATION MANUAL 10 30kVA 208V 60Hz...
Страница 54: ...Installation Drawings 48 Figure 27 Location of internal batteries Battery 417mm 687mm 186...
Страница 64: ...Specifications and Technical Data 58 NOTES...
Страница 65: ...Specifications and Technical Data 59...
Страница 66: ...Specifications and Technical Data 60...
Страница 67: ......