(3-way) Valve
Service Manual
51
(2) Evacuation
(All amount of refrigerant leaked)
• Procedure
1. Confirm that both the liguid side valve and gas
side valve are set to the opened position.
2. Connect the vaccum pump to the center hose of
the manifold gauge.
3. Connect the service port of the gas side valve to
the low side of the gauge.
4. Evacuation for approximately one hour.
- Confirm that the gauge needle has moved
toward-76 cmHg (vacuum of 4 mmHg or less).
5. Close the Low handle of the gauge turn off the
vacuum pump, and confirm that the gauge
needle does not move(approximately 5 minutes
after turning off the vacuum pump).
6. Disconnect the charge hose from the vacuum
pump.
- Vacuum pump oil.
If the vacuum pump oil becomes dirty or
depleted,replenish as needed.
7. Mount the valve caps and the service port caps.
Lo
Open
Open
Vacuum pump
2-Way
valve
Outdoor unit
Liquid side
Indoor unit
Gas side
3-Way
valve
CLOSE
OPEN
Содержание LC240CP
Страница 20: ...20 Ceiling Cassette Air Conditioner Wiring Diagrams 1 Indoor Unit LCN240CP Wiring Diagrams ...
Страница 21: ...Service Manual 21 Wiring Diagrams LCU240CP LCU380CP 2 Outdoor Unit ...
Страница 53: ...Electronic Control Device Service Manual 53 Electronic Control Device Ceiling Cassette Type Main P C B ASM ...
Страница 64: ...P No 3828A20911A Printed in Korea ...