Location of anchor bolt
n
Installation foot (Location of anchor bolt)
Foundation for Installation
• Fix the unit tightly with bolts as shown below so that unit will not fall down due to earthquake or gust.
• Use the H-beam support as a base support
• Noise and vibration may occur from the floor or wall since vibration is transferred through the installation
part depending on installation status. Thus, use anti-vibration materials (Anti-vibration pad) fully (The base
pad shall be more than 200mm).
A
B
D
E
F
G
C
Ensure that the corner part can be securely mounted. Otherwise, the support for
installation may be bent.
Obtain and use the M10 anchor bolt.
The corner was not properly mounted.
Outdoor unit (Insert the cushion pad between outdoor unit and base support to ensure that
anti-vibration may be done in a wide area)
Pipe and wiring space (in case of piping and wiring on the floor surface)
H-Beam support
Concrete base support
G
Foundation bolt executing method
200
Nut
75
75
200
Spring washer
Frame
Anti-vibration
materials
Four bolt are
required
3 thread ridges
H-Beam
Concrete
base
100
WARNING
• Be sure to install unit in a place strong enough to withstand its weight.
Any lack of strength may cause unit to fall down, resulting in a personal injury.
• Have installation work in order to protect against a strong wind and earthquake. Any installation
deficiency may cause unit to fall down, resulting in a personal injury.
• Especially take care for support strength of the floor surface, water drain processing (processing of
water flown out from the outdoor unit during operation) and paths of the pipe and wiring when mak-
ing a base support.
• Don't use a tube or pipe for water drain in the base pan and perform water drain processing by
using the drain path. Water drain may not be done due to freezing of a tube or pipe.
(Unit : mm)
723
UV : 516
UV1 : 362