5
2 SITE LOCATION AND PROVIDING POWER
2.2 Connecting Input Power
2.2.1 Per local electrical code and site specifications connect power to voltage
sense input and panel power input.
2.2.2 There are separate power inputs for meter reference voltage and panel power
to allow the hub and meter to remain powered if the circuits being monitored
need to be off.
2.3 Connecting Current Transformers
2.3.1 CT inputs are located next to the power input section on the lower DIN rail.
2.3.2 CT should be wired per manufacturer directions indicated below. CT terminals
are clearly labeled CT1 (X1/X2), CT2 (X1/X2), and CT3 (X1/X2).
Содержание A8810-41M
Страница 2: ......