1 - RECEIPT

1.1 - Inspection

On receiving your generator, check that it has not been
damaged in any way during transportation. 
If there is any obvious damage, contact the carrier (a
claim can be made on their insurance) and after a visual
check, turn the generator by hand to detect any possible

fault. 

1.2 - Identification

GEARLEC / TRACTELEC are identified by a self-adhesive

black/orange nameplate on the machine cover. 
Check that the nameplate on the machine corresponds

to your order. 
GEARLEC / TRACTELEC  incorporate alternators from
the PARTNER range, especially designed for agricultural
use. The generator is identified by another metal name-
plate riveted on the casing.
The  GEARLEC / TRACTELEC range comprises 2 pro-
ducts :
- the GEARLEC : GT 41.1, GT 42.1, GT 44.1 is intended
for the builder of the generator set or installer,
- the TRACTELEC  is a finished product, ready to use,
and available :
- as a fixed version :  TF.1- 27 ,  TF.1-38 and TF.1-70
(without 3-point chassis),  
- as a mobile version : TM.1- 27 , TM.1-38  and TM.1-70
(with chassis enabling the TRACTELEC to be fixed to a
tractor's 3-point linkage. 

1.2.1 - Dimensions
The dimensions of the GEARLEC range are set out in
catalogue ref : 626 and those of the TRACTELEC range

in catalogue ref : 634.

4

MAINTENANCE

GEARLEC / TRACTELEC . 27, 38, 70 kVA

COUNTER

EXTERNAL SUPPLY

INTERNAL SUPPLY

4-POLE REVERSING SWITCH (OPTIONAL) 

TRACTELEC INTERNAL CONNECTIONS

001254836

1

2

3

N

T

V

Blue

Blue

Brown

Brown

Brown

V/J

R 791

R.C. 
BREAKER

1.3 - Electrical diagram/coupling/regulator

Both the electrical diagram for the alternator and the
terminal connections are defined in the maintenance
manual ref : 1383. For TRACTELEC, electrical connection
should be performed in accordance with the diagram
(Fig. 1). Electrical installations must conform to the legis-
lation in force in the country of use.

- A current reversing switch must be placed
between the mains and the GEARLEC
equipped with a panel, or TRACTELEC. 

1.4 - Storage

Before commissioning, machines must be : 
- sheltered from humidity : for relative humidities greater
than 90%, the machine insulation can drop very quickly
and become virtually non-existent at around 100%;
check the anti-rust protection on unpainted parts. 
For a very long storage period, it is advisable to place
the motor in a sealed package (eg. heat-sealed plastic)
containing dehydrating sachets, protected from frequent
significant temperature variations to prevent formation of
condensation during storage.
- In the event of surrounding vibrations, try to reduce the
effect of these vibrations by placing the generator on a
damping support (eg. rubber plate) and turn the rotor
slightly once a fortnight to prevent the bearing rings from
being marked.

Fig. 1

Содержание Gearlec

Страница 1: ...GEARLEC TRACTELEC GEARLEC TRACTELEC 27 38 70 kVA R f 3185 4 33 a 6 99 These instructions should be given to the end user Installation and maintenance Installation and maintenance...

Страница 2: ...ristics 5 2 5 Options electrical mechanical and electronic 5 3 INSTALLATION COMMISSIONING 3 1 Mounting 5 3 2 Checks before first use 6 3 3 Setting 6 3 4 Commissioning 6 4 SERVICING MAINTENANCE 4 1 Saf...

Страница 3: ...ing in the context of the EMC LVD Low Voltage Directive and MACHINERY directives as a machine A certificate of conformity can be supplied on request Safety measures Before using your generator for the...

Страница 4: ...E GEARLEC TRACTELEC 27 38 70 kVA COUNTER EXTERNAL SUPPLY INTERNAL SUPPLY 4 POLE REVERSING SWITCH OPTIONAL TRACTELEC INTERNAL CONNECTIONS 001254836 1 2 3 N T V Blue Blue Brown Brown Brown V J R 791 R C...

Страница 5: ...Use a lifting system which respects the machine environment terminal box 3 1 2 Coupling The GEARLEC or TRACTELEC is coupled to an agricultural tractor by means of a universal joint not supplied A hous...

Страница 6: ...supplied has its own switchgear or starter system for motors The earth must meet electrical standards and safety rules in force in that country The GEARLEC version must also be fitted with a control...

Страница 7: ...e the ambient temperature If this is exceeded the machine must be stopped and checked 4 2 5 Storage Do not clean the TRACTELEC with a water jet spray Put away your machine in a dry airtight place to a...

Страница 8: ...e circlips 565 and dismantle the gear pinion bearing assembly using a U 35 FACOM extractor Check the state of the sealing ring 569 and lipseal 572 4 7 2 Reassembly Fit the inner bearing retainer 568 a...

Страница 9: ...SOMER MOTORS Usine de Sillac Alternateurs 16015 ANGOULEME CEDEX FRANCE Tel 33 05 45 64 45 64 Helpline 33 05 45 64 43 69 Fax 33 05 45 64 43 24 References for the various parts can be found on the expl...

Страница 10: ...l circlips 48 1 Upper part of cover 567 1 Bearing 367 1 Inspection door circuit breaker side 568 1 Inner bearing retainer 368 1 Cover door socket side 569 1 Sealing ring 546 1 Chassis 572 1 Lipseal 54...

Отзывы: