MSAV BLOWER OPERATION
G Blower Demand:
1- 24VAC is routed from thermostat blower G.
2- K117 relay is energized. K117 N.O. contacts close and
24VAC is routed through K186 and K36 N.C. contacts
to A96 inverter terminal RL. Blower operates in low
speed.
Y1 Cooling Demand:
3- Blower demand initiates low speed in the same manner
as G Blower Demand.
Y2 Cooling Demand:
4- K186 relay is energized and K186 N.O. contacts close.
5- The blower demand closes K117 N.O. contacts.
24VAC is routed through K117 and K186 closed con
tacts to A96 inverter terminal RH. Blower operates in
high speed.
W1 Heating Demand:
6- K36 relay is energized and K36 N.O. contacts close.
The blower demand closes K117 N.O. contacts.
24VAC is routed through K117 and K36 closed con
tacts to A96 inverter terminal RH. Blower operates in
high speed.