5− Furnace Control (A3) 80UHG−1 Model

80UHG units are equipped with an integrated ignition/blower
control (EGC-2) which controls ignition, safety circuits,
blower operation, fan off timing, and allows for thermostat
connection and troubleshooting. The EGC-2 is a printed
circuit board which is divided into two sections, 120 and
24VAC. Line voltage comes into the board on the 120VAC
side. See figure 10. Terminal designations are listed in
tables 6 and 7.

Ignition Control

80UHG units use the EGC−2 direct spark integrated
ignition control. The EGC−2 controls and monitors the
entire sequence of operation. On a call for heat from the
thermostat the control monitors the combustion air in-
ducer prove switch. The control will not begin the heat-
ing cycle if the prove switch is closed (by-passed). Once
the prove switch is determined to be open, the combustion
air inducer is energized. When the differential in pressure
across the prove switch is great enough, the prove switch
closes and a 15 second pre-purge period begins. If the
prove switch does not close within 2 1/2 minutes, the con-
trol goes into 5 minute watchguard. After the pre-purge pe-
riod, the gas valve will open and ignition (spark) will be at-
tempted for 10 seconds. After ignition, the control initiates a
ten second flame stabilization period. The flame stabi-
lization period allows the burners to heat up and the
flame to stabilize. Once flame is established, the control will
constantly monitor the burner flame using flame rectification.
Flame failure response time is 0.8 seconds.

If the initial attempt for ignition fails, the sequence is re-
peated up to five times. After the fifth trial, the control goes into
Watchguard"*. During watchguard mode, the entire unit will
be de-energized for one hour. After one hour the control will
repeat the ignition sequence. Watchguard may be manually
reset by breaking and remaking thermostat demand.

*NOTE−If flame is established beyond the 10 second flame
stabilization period then lost, the control resets for five more
ignition trials. The control can be reset five times during one
unsatisfied thermostat demand, providing a maximum
of 25 trials for ignition.

Safety Circuits

During the entire heating demand the control monitors the
safety circuits. If the primary or secondary heating limits
open, the control de-energizes the main gas valve and
combustion air blower while the indoor blower remains en-
ergized. When the limit automatically resets, the ignition se-
quence also resets. If either of the limits trip five consecu-
tive times during one unsatisfied thermostat demand, the
control will go into watchguard for one hour.

The control monitors main valve voltage. If voltage is sensed

when no voltage should be present, the control de-energizes
the combustion air inducer  which terminates voltage to the
valve. The system goes into hard lock-out which is reset only
by removing power to the unit.

If flame is sensed when no flame should be present, the con-
trol will energize the combustion and indoor blowers. The
unit will remain locked in this sequence until the flame is no
longer sensed or the main power is turned off to reset the
control.

The roll-out circuit is also monitored by the EGC-2 control. If
the switch opens, the control will de-energize the gas
valve, combustion air inducer, and indoor blower. The
unit will remain de-energized until the switch is manual-
ly reset.

DANGER

Shock hazard. Avoid personal injury. Make sure to
disconnect power before changing fan off" timing.

Blower Operation / Fan Off Timings

Fan off" timing (time that the blower operates after the heat
demand has been satisfied) can be adjusted by moving the
jumper on the EGC-2 blower control board. Figure 9 shows
the various fan off" timings and how jumper should be posi-
tioned. To adjust fan off " timing, gently disconnect jumper
and reposition across pins corresponding with new timing.
Unit is shipped with a factory fan off" setting of 180  seconds.
Fan on" time is factory set at 45 seconds following the
opening of the main gas valve and is not adjustable.

Fan off" time will affect comfort and efficiency and is ad-
justable to satisfy individual applications. The fan off" tim-
ing is initiated after a heating demand but not after a cool-
ing demand.

NOTEIf fan off" time is set too low, residual heat in
heat exchanger may cause primary limit S10 to trip, re-
sulting in frequent cycling of blower. If this occurs, adjust
blower to longer fan off" time setting.

FIGURE 9

FAN-OFF TIME ADJUSTMENT

180

60

120

90

To adjust fan-off timing:

Remove jumper from EGC-2 and select

one of the other pin combinations to

achieve the desired time.

TIMING

JUMPER

TIMING PINS

(seconds)

Leave jumper off for

240 second fan-off timing.

Содержание 80UGH

Страница 1: ...Nitrogen Oxides NOx Standards and California Sea sonal Efficiency requirements All units use a redundant gas valve to assure safety shut off as required by A G A or C G A Units may be installed in up...

Страница 2: ...46J66 15 lbs 8 kg SPECIFICATIONS Model No 80UHG3 4 X 100 80UHG4 5 X 100 80UHG3 4 X 120 80UHG4 5 X 120 Input Btuh kW 100 000 29 3 120 000 35 2 Output Btuh kW 82 000 24 0 98 400 28 8 A F U E 80 1 80 0...

Страница 3: ...375 20 50 1370 645 1180 555 980 460 790 375 25 62 1350 635 1160 545 970 460 780 370 30 75 1330 630 1140 540 955 450 770 365 40 100 1280 605 1095 515 925 435 750 355 50 125 1210 570 1040 490 900 425 72...

Страница 4: ...lace Also see Filter Air Resistance table FILTER AIR RESISTANCE cfm L s in w g Pa 0 0 0 00 0 200 95 0 01 2 400 185 0 03 7 600 280 0 04 10 800 375 0 06 15 1000 470 0 09 22 1200 560 0 12 30 1400 655 0 1...

Страница 5: ...BOX SECONDARY LIMITS FRONT ACCESS PANEL DOOR INTERLOCK SWITCH CONTROL BOARD TRANSFORMER PROVE SWITCH 80UHG PARTS IDENTIFICATION FIGURE 2 HEAT EXCHANGER COMBUSTION AIR INDUCER MANIFOLD ROLLOUT SWITCH...

Страница 6: ...protect the furnace s electronic controls Precautions will help to avoid control exposure to electrostatic dis charge by putting the furnace the control and the technician at the same electrostatic po...

Страница 7: ...pen the combustion air inducer is energized When the differ ential in the prove switch is great enough the prove switch closes and a 15 second pre purge begins If the prove switch is not proven within...

Страница 8: ...ed OR Pressure switch closed prior to activation of combustion air blower ALTERNATING SLOW FLASH ALTERNATING SLOW FLASH Watchguard burners fail to ignite SLOW FLASH OFF Flame sensed without gas valve...

Страница 9: ...gnal is sensed NOTE The 80UHG furnace contains electronic com ponents that are polarity sensitive Make sure that the furnace is wired correctly and is properly grounded PARK TERMINAL DESIGNATIONS COOL...

Страница 10: ...its If the primary or secondary heating limits open the control de energizes the main gas valve and combustion air blower while the indoor blower remains en ergized When the limit automatically resets...

Страница 11: ...is a heating demand On Flash Primary or Secondary Limit Switch Open Auto Reset Switch Flash Off Pressure Switch Watchguard pressure switch opened during operation Alternate Flash Alternate Flash Watch...

Страница 12: ...P 1 2 1 3 1 4 5MFD 370V 5MFD 370V 7 5MFD 370V 80UHG5 6 80UHG4 80UHG4 5 1 2 7 5MFD 370V 3 4 40MFD 370V 3 4 40MFD 370V FIGURE 11 SUPPLY AIR BLOWER AND SECONDARY LIMITS Front Bottom Right Left Top Back B...

Страница 13: ...t point will be printed on the limit Two limits are supplied in each furnace 80UHG3 80UHG4 and 80UHG4 5 model units built prior to Apri 1999 will have one each of style shown in figures 13 and 14 If s...

Страница 14: ...DEL SHOWN FIGURE 18 SPARK ELECTRODE SPARK ELECTRODE TO BURNER GAP 80UHG 1 MODEL SHOWN BURNER FLAME SENSOR TO BURNER GAP BURNER FLAME SENSOR SPARK ELEC TRODE 5 16 in 7 mm 5 16 in 7 mm 13 Combustion Air...

Страница 15: ...ard 80UHG 1 units are equipped with a direct spark igni tion system Do not attempt to light manually 1 STOP Read the safety information at the beginning of this section 2 Set thermostat to lowest sett...

Страница 16: ...to check for gas leaks D Testing Gas Supply Pressure When testing supply gas pressure connect test gauge to inlet pressure tap field provided See figure 20 Check gas line pressure with unit firing at...

Страница 17: ...amp DC meter is needed to check the flame signal on the ignition control Flame microamp signal is an electrical current which passes from the furnace control through the sensor during unit opera tion...

Страница 18: ...mperature is too low decrease blower speed If temperature is too high first check the firing rate Provided the firing rate is acceptable in crease blower speed to reduce temperature To change blower s...

Страница 19: ...in the heat exchanger cleaning is not recommended Removal is for inspection only NOTE Use papers or protective covering in front of fur nace while cleaning furnace To clean burners 1 Remove screws ho...

Страница 20: ...ting in gas leaks fire or explosion C Supply Air Blower 1 Check and clean blower wheel 2 Motors used on the Lennox 80UHG series units are permanently lubricated and need no further lu brication D Flue...

Страница 21: ...n control energizes the combustion air inducer B6 When the combustion air inducer nears full speed combustion air prove switch S18 closes Switch must close within 2 1 2 minutes or control goes into 5...

Страница 22: ...OR BLOWER WITH DELAY OFF DIAG CODE 1 OFF 2 FLASHING C A B PRESSURE SWITCH OPEN IS 5 MINUTE RESET PERIOD COMPLETE INDOOR AIR BLOWER ON Fixed 45 second delay PRIMARY SECONDARY LIMITS MONITORED IN HEAT C...

Страница 23: ...MOSTAT CONTROL ENERGIZES SYSTEM FAN AT HEATING SPEED ACC TERMINAL ENERGIZED THERMOSTAT CALLS FOR HEAT LED Slow flash rate REMAINS UNCHANGED THROUGHOUT SEQUENCE THERMOSTAT CALLS FOR COOLING SYSTEM FAN...

Страница 24: ...guard Pressure Switch delay Once S18 closes a 15 second pre purge follows 4 SureLight control energizes ignitor A 20 second warm up period begins 5 Gas valve opens for a 4 second trial for ignition i...

Страница 25: ...AS VALVE OFF COMBUSTION AIR INDUCER ON INDOOR BLOWER ON HEATING SPEED LED 1 SLOW FLASH LED 2 OFF GAS VALVE OFF COMBUSTION AIR INDUCER OFF INDOOR BLOWER OFF WITH DELAY LED 1 OFF LED 2 SLOW FLASH Sequen...

Страница 26: ...S CONTROL FAILED TO SENSE FLAME FOR FIVE CONSECUTIVE TRIES DURING A SINGLE HEAT DEMAND WATCHGUARD MODE GAS VALVE OFF COMBUSTION AIR INDUCER OFF INDOOR BLOWER OFF WITH DELAY LEDs SIGNAL WATCHGUARD FAIL...

Страница 27: ...D SLOW FLASH RATE REMAINS UNCHANGED THROUGHOUT COOLING CYCLE THERMOSTAT CALLS FOR COOLING COMPRESSOR CONTACTOR AND SYSTEM FAN ENERGIZED WITH 0 SECOND DELAY COOLING SPEED EAC H TERM ENERGIZED COMPRESSO...

Страница 28: ...THERMOSTAT CALLS FOR HEAT W THERMOSTAT CALLS FOR COOLING THERMOSTAT OPENS SYSTEM FAN SWITCHED TO COOL H SPEED EAC H TERM REMAINS ON THERMOSTAT OPENS MANUAL FAN SELECTION MADE AT THERMOSTAT CONTROL G...

Страница 29: ...he roll out switch by pushing the top button ACTION 2 Determine the cause of the roll out switch activation before leaving furnace code 1 2 2 Roll out switch failure ACTION 1 Check continuity across r...

Страница 30: ...WER DOES NOT ENERGIZE Condition Possible Cause Corrective Action Comments 2 1 Unit operates with a cooling or con tinuous fan demand Combustion air inducer will not start with a Heating demand Diagnos...

Страница 31: ...e pressure switch failure code 2 5 minutes after heating demand 3 1 2 Pressure switch does not close due to obstructions in the pressure lines ACTION 1 Remove any obstructions from the the pressure li...

Страница 32: ...switch code LED 1 Off LED 2 Slow Flash 5 1 1 Low pressure differential at the pres sure switch ACTION 1 Check for restricted exhaust vent Remove all blockage ACTION 2 Check for proper vent sizing See...

Страница 33: ...3 4 Burners are not properly located in the burner box ACTION 1 Check that the burners are firing into the center of the heat exchanger openings Cor rect the location of the burners if necessary 5 4...

Страница 34: ...Action Comments 7 0 Indoor blower fails to operate in continuous fan cooling or heating mode 7 1 1 Miswiring of furnace or improper con nections at control or indoor blower motor ACTION 1 Correct wir...