Checking Central Heating Operation

Flow diagram 3

Checking the Fan/Flue Gas Circuit

Wait 2 minutes

Put CH temperature selector

to maximum

Ensure external controls

are calling for heat

Is LED4 flashing?

Does CH pump run?

YES

YES

Go to chart 3

Is relay RY101

switch on

Check and if

necessary replace

main board

NO

Is LED4 flashing?

Check and if is necessary

replace main board

YES

NO

Is relay RY100

switch on

NO

YES

Go to chart 3

NO

Check

limit thermostat

YES

Check pump

wiring

connection

NO

Check and if

necessary

replace pump

Does fan run?

Is relay RY100 switch ON?

NO

Go to charts 2

NO

Is 230V present across

fan terminals?

YES

Check air pressure

switch wiring connection in N.O.

NO

Check and if

necessary replace

air pressure switch

NO

Check and if

necessary replace fan

YES

Is air pressure switch

activated?

YES

NO

Check and if

necessary replace

air pressure switch

YES

Differential air pressure

across the air pressure

switch is greater than

180 Pascal?

Go to chart 5

YES

NO

Check and clean fan

Check flue and air

intake are correct

and clean

Check Venturi and

air pressure switch

tubes are clean

Check restrictor

is correct

Содержание Externa 30 O

Страница 1: ...WALL HUNG GAS FIRED SEALED BOILER FOR CENTRAL HEATING OPERATING INSTALLATION AND MAINTENANCE INSTRUCTIONS cod 3540T54 0 04 2009 Rev 00 7 Externa 30 O...

Страница 2: ...ations disconnect the appliance from the mains power supply using the system switch and or the corresponding on off devices In the event of faults and or poor ope ration of the appliance it should be...

Страница 3: ...2 2 Place of installation 7 2 3 Water connections 7 2 4 Gas connection 9 2 5 Electrical connections 9 2 6 Flues 11 3 SERVICE AND MAINTENANCE 12 3 1 Settings 12 3 2 Commissioning 14 3 3 Maintenance 15...

Страница 4: ...er pressure switch temperature sensors and safety thermostat The microprocessor based control system means that the operation of the appliance is almost comple tely automatic The central heating outpu...

Страница 5: ...r and the central heating system alternatively drain only the domestic hot water and place the special antifreeze fluid in the central heating system 1 4 Settings Summer Winter setting and system temp...

Страница 6: ...d at least biennial checks on the combustion device Please refer to Chap 3 3 in this manual for further information The casing the control panel and the aesthetic parts of the boiler can be cleaned us...

Страница 7: ...all must provide stable and effective support of the appliance Upon request a metal wall drilling template is available This is used exclusively to trace the holes for fastening the appliance onto the...

Страница 8: ...the system In the boiler From the system In the boiler In the boiler From the system A F C D E F E D B C A Connection with cocks Connection with nipples A Female pipe coupling C OR gasket D OT 58 stop...

Страница 9: ...ons check that the appliance is configured for operation with the type of fuel available and carefully clean all the gas pipes in the system to remove any residues that may affect the correct operatio...

Страница 10: ...3 mm Max 3A fuses must be installed between the boiler and the line The correct polarity must be followed PHASE brown wire NEUTRAL blue wire EARTH yellow green wire in the electrical connections If t...

Страница 11: ...on of the boiler it is necessary to mount the concentric terminal followiong instruc tioins below 1 Mount and fix boiler on the wall 2 Insert rubber gasket on terminal 3 Insert terminal on appliance c...

Страница 12: ...pressures in the burner ref corresponding paragraph setting the values indicated in technical data table for the type of gas used 3 Change the position of Jumper 02 on the electronic board ref corres...

Страница 13: ...5 Factory set do not tamper X6 X1 X2 X3 X4 1 2 1 2 1 3 1 2 3 4 5 6 7 8 9 10 1 2 3 4 5 6 7 8 9 10 11 12 13 2 1 X5 L1 L2 L3 L4 L5 Transformer P2 DHW X12 1 2 P3 P5 P4 JP02 JP01 JP03 1 2 3 4 5 6 7 8 9 X10...

Страница 14: ...ntenance operations which may have required the disconnection from the systems or intervention on the safety devices or parts of the boiler Before igniting the boiler Open any on off valves between th...

Страница 15: ...pening a hot water tap the heating pump switches off the domestic hot water pump starts and there is regular production of domestic hot water Shut down Close the gas cock upstream of the boiler and di...

Страница 16: ...tats gas valve and circulation pump After these checks ensure that there are no gas leaks Analysis of combustion Two test points are installed inside the boiler one for the flue gases and the other fo...

Страница 17: ...5 bar Check water pressure switch wiring connection NO Does fan run at full speed NO Go to CHART 2 NO YES Does CH Pump run If the boiler temperature is less than 5 C frost protection is activated Dis...

Страница 18: ...eck limit thermostat YES Check pump wiring connection NO Check and if necessary replace pump Does fan run Is relay RY100 switch ON NO Go to charts 2 NO Is 230V present across fan terminals YES Check a...

Страница 19: ...r light now Is flame present before lockout condition NO YES NO Check and if necessary replace safety thermostat Check electrodes and leads for damage and correct connection Check and if necessary rep...

Страница 20: ...09 Rev 00 4 CHARACTERISTICS AND TECHNICAL SPECIFICATIONS 4 1 Dimensions and fittings fig 7 Key 1 CH flow 2 Filling cock 3 Gas inlet 4 CH return Top View Bottom View 99 85 428 850 96 158 270 236 5 326...

Страница 21: ...49 50 7 11 74 44 14 19 187 22 82 81 36 20 21 26 27 114 34 Threaded adapter ISO 7 1 27 Copper heat exchanger 28 Flue collector from heat excanger 32 Central heating pump 34 Central heating temperature...

Страница 22: ...l heating outlet 11 Central heating inlet 16 Fan 20 Burner assembly 29 Flue gas outlet manifold 32 Central heating pump 34 Central heating temp sensor 43 Air pressure switch 44 Gas valve 49 Safety the...

Страница 23: ...Maximum central heating operating temperature C 100 Index of protection IP X5D Power supply Power supply voltage frequency V Hz 240 50 60 Max Power Absorbed W 125 Central heating system fittings inche...

Страница 24: ...ure drop Discharge head available to system fig 10 fig 11 kW kPa 18 19 20 21 22 23 0 5 1 0 1 5 2 0 2 5 3 0 3 5 9 10 11 12 13 14 15 16 17 8 24 25 26 27 28 29 30 31 32 33 34 Universal LP Gas Natural Gas...

Страница 25: ...9 10 1 2 3 4 5 6 7 8 9 10 11 12 13 2 1 X5 TEST X12 1 2 1 2 3 4 5 6 7 8 9 X10 W O V R X8 X7 81 82 PMF03F JP02 JP01 JP03 Nat LPG X11 240V 24V 240V 24V BR Blue BR Blue BR Blue MV1 MV2 MV3 MV4 Blue BR Blu...

Страница 26: ......

Страница 27: ......

Страница 28: ...Ferroli spa 37047 San Bonifacio Verona Italy Via Ritonda 78 A tel 39 045 6139411 fax 39 045 6100933 www ferroli it...

Отзывы: