Page
14
ALTO Ultima
®
Tower
| Assembly Guide
Step 7.1
Working from the temporary
platform, install a 4 rung main frame
& a 4 rung ladder frame onto the
first set of 5 rung frames. Then, clip
2 standard diagonal braces on. The
start position of the brace should
be on the same rung height as the
finishing position from the brace
below - running in the same parallel
direction.
Step 7.2
Install a 2nd platform 4 rungs above
the first platform. Using the 3T
method install 4 guardrails to the
upper platform. If a 3.4m tower is
being assembled, go to step 10.
Proceed to Step 8
Build Method C
3.4m, 5.4m, 7.4m, 9.4m, 11.4m