AIR SUPPLY SET UP
Locate the air regulator on the rear of the vertical column and connect the air supply.
1. Once all the air fittings are secure, turn the air supply on to the machine. The gauge
should read 90 PSI.
2. If the reading is more or less, adjust the regulator to 90 PSI. If the reading is more or less
adjust the regulator to 90 PSI
Incoming air from the air compressor must be clean and dry. Use all precautions and
water traps as necessary.
LOADING/UNLOADING TABLES
After electric and air supply is setup if loading or unloading tables were ordered install them
now.
Make sure the tables are level and precise in alignment with the feeder unit.
HEAD CHANGE
If both the ferrous and non-ferrous heads were purchased and you need to change out the head
please contact DAKE for instructions.
BLADE INSTALLATION
WARNING
Before performing the following operations, the electrical supply must be
LOCKED OUT and always were gloves when installing a new blade.
Blade Installation for a Ferrous Head:
1. Open the clear protective cover and magnetically latched blade guard.
2. Remove the spindle flange bolt using the socket wrench provided.
3. Remove the blade flange and wipe the blade surface of the flange and spindle clean.
4. Carefully slide the blade up through the coolant distribution tubes. Be careful not to bend
the tubes.
a. Make sure teeth are facing the correct direction for counter-clockwise rotation.
5. With a rolling motion of the blade counter-clockwise, push against the chip brush and
slide blade over the spindle shoulder.
6. Rotate the blade on the shoulder to align the two large drive pin holes.
7. Insert the flange pins through the drive pin holes and insert bolt, hand tighten at this
point.