 ALTOSONIC V  

ELECTRICAL INSTALLATION

3

Mains connection of the UFC-V (hazardous environment) 

 

Use a 3 wire power cable with PE (protective earth conductor) in accordance with the Ex- 
and possible local regulations.  

 

The diameter of the power cable has to be in accordance with the nominal diameter of the 
cable clamp. 

 

For connection diagram refer to the addition to these instructions or see table below. 

 

Only the PE conductor (protective earth conductor) shall be connected to the indicated PE 
terminal in the signal converter housing. 

 

Terminal 

Description 

Connect to 

24V AC/DC (non SELV) 115 / 230V AC
UFC-V X1 PE  

PE  

System safety ground

UFC-V X1 N  

N  

External power supply    neutral 

UFC-V X1 L  

L  

External power supply….live 

24V AC/DC (SELV) 
UFC-V X1 FE 

FE 

Not connected

UFC-V X1  - 

 - 

External power supply, neutral 

UFC-V X1  + 

 + 

External power supply, live 

 

Mains connection of the UFP-V and the I/O rack (non-hazardous environment) 
The mains connection terminals of the UFP-V and the I/O modules on the I/O rack are situated 
on the back side of the rack. Use a 3 wire power cable with PE (protective earth conductor) in 
accordance with local regulations. Only the PE conductor (protective earth conductor)  shall be 
connected to the indicated PE terminal in the signal converter housing. 

 

Terminal 

Description 

Connect to 

Mains voltage 115 / 230V AC 
I/O-rack X10b with IEC socket 

UFP-V via the IO-rack

UFP-V X10a IEC inlet 

UFP-V I/O-rack X1 PE  

PE 

System safety ground 

UFP-V I/O-rack X1 N  

External power supply     neutral 

UFP-V I/O-rack X1 L  

External power supply     live 

 

3.4

 

Connecting Flow Sensor to Flow Converter 

The electrical connection between the Flow Sensor and the Flow Converter is by way of factory-
supplied sensor signal cables: refer to the connection diagrams. Use pre-certified EEx-d cable 
glands. 
An equipotential bonding shall be made between the UFS-V and the UFC-V. The connection 
between the Flow Sensor UFS-V and the Flow Converter UFC-V consists of three sensor cables. 
Each cable contains 4 coaxial cables with preassembled SMB connectors. The cables have to be 
connected to the Flow Sensor UFS-V through the cable glands to connector X1. All cables are 
numbered in the same way as the connector X1 is numbered. The cables must run through the 
special shield connector in such way that the shield is connected to the shield connectors (see 
picture below). 
The shield shall be clamped to the ground rail using the provided connectors. (If applicable, two 
of the coaxial cables preassembled with SMB connectors are for spare). 
 

Содержание ALTOSONIC V

Страница 1: ...Processor Electrical Mechanical Installation Soware Version 0300 ALTOSONIC V Installation Manual ALTOSONIC V 5 beam ultrasonic flowmetering system Operating and installation instructions UFC V EEx Flo...

Страница 2: ...ge Install the product securely and stable Install and connect cabling proper to exclude damage or harmful situations If the instrument does not operate normally refer to the service instructions or r...

Страница 3: ...stem may lead to loss of warranty In addition the Terms and Conditions of Sale are applicable and are the basis for the purchase contract If flow meters need to be returned to KROHNE please note the i...

Страница 4: ...Certificate of system calibration data This instrument is developed and manufactured by KROHNE Altometer Kerkeplaat 12 3313 LC Dordrecht The Netherlands For information maintenance or service please...

Страница 5: ...3 Electrical installation 13 3 1 Overview of connections 13 3 2 Installation location and wiring considerations 13 3 3 Power connection 14 3 4 Connecting Flow Sensor to Flow Converter 15 3 5 Connecti...

Страница 6: ...its environment 1 2 Unpacking and inspection This product has been thoroughly inspected and tested before shipment and is ready for operation After carefully unpacking inspect for shipping damage bef...

Страница 7: ...d the supplied I O rack configuration may only be operated in a safe non hazardous area The I O rack contains the additional I O modules for a safe separation between hazardous and non hazardous envir...

Страница 8: ...the Operating and Installation Instructions for use in hazardous areas For the non hazardous area equipment UFP V and I O rack the following applies This product is designed for use in accordance with...

Страница 9: ...29 of the housing Use up to an altitude of 2000 m above sea level Operation ambient temperature range 0 C to 50 C Use with a relative humidity of 5 85 50 C non condensing Storage temperature range 20...

Страница 10: ...and regulations must be respected The sensor axis must be approximately horizontal even if the flowmeter is installed in slightly ascending horizontal pipe runs The position of the flow sensor in the...

Страница 11: ...eter of the flanges of the flow sensor Correct gaskets shall be used If inlet and outlet sections are ordered they will be used during the calibration and must be installed identically in the final ap...

Страница 12: ...g device to keep the electronics within its working temperature range If because of indirect heating e g by sunlight the housing temperature can become 65 C a sunshade is recommended to prevent the el...

Страница 13: ...ons Do not kink the cables Provide a water drip point U bend in cable Conduits The described standard version of ALTOSONIC V is equipped with cable glands for the use of harmonized cable In countries...

Страница 14: ...ter UFC V and Flow Sensor UFS V PE Protective conductor incorporated in power supply cable Coax Sensor cables factory supplied Bonding wire Connection cable cross section 4 mm2 10 AGW Cu equipped with...

Страница 15: ...conductor protective earth conductor shall be connected to the indicated PE terminal in the signal converter housing Terminal Description Connect to Mains voltage 115 230V AC I O rack X10b with IEC so...

Страница 16: ...ATION 3 Connection box on Flow Sensor UFS V and shield grounding clamp On the side of the Flow Converter UFC V the cables must be connected in the same way as in the Flow Sensor UFS V but on connector...

Страница 17: ...04 2012 www krohne com 17 ALTOSONIC V ELECTRICAL INSTALLATION 3 Connector X1 X2 of Flow Converter UFC V 24 VDC Connector X1 X2 of Flow Converter UFC V 110 230 VAC...

Страница 18: ...in the I O rack to the MTL5073 module A1 as shown below This connection has to be made with a shielded 4 wire cable not supplied In the Flow Sensor UFS V and the I O rack Flow Computer UFP V this cab...

Страница 19: ...wire must also be connected with the shield to the shield connectors on both sides The cable has to be connected according to the table below UFC V X1 Wire I O rack UFP V connection terminal position...

Страница 20: ...ed with flowmeter 3 7 Connecting the I O rack to the Flow Computer UFP V For connecting the Flow Computer UFP V I O rack to the Flow Computer UFP V the pre wired connectors on the Flow Computer UFP V...

Страница 21: ...uts Mp103 card DB9 Connector 1 TTL compatible Umax 12 V Imin 1mA Imax 10mA Relay outputs MP103 card DB9 Connector 2 Switchable Umax 150Vdc 125Vac Imax 0 2A Current output MP103 card DB9 Connector 3 Ac...

Страница 22: ...MP103 Analog inputs AD812 card PCLD 780 wiring board Pmax limit for used 250 ohm resistors 0 2 W Maximum Overvoltage continuous 7V Usually connected through barriers Analog outputs AD812 card PCLD 78...

Страница 23: ...d the auxiliary apparatus like temperature pressure and density measuring instruments The results are displayed on the screen and represented in a train of output pulses with a calibrated one pulse vo...

Страница 24: ...current Note Modules may be intrinsically or non intrinsically safe Custody transfer certified I O modules that may be used are Made by MTL Cenelec FM and CSA Ex i certified modules MTL 5073 4 Pt 100...

Страница 25: ...ire cross section chosen to fit The field cabling shall be according to the local regulations and practice The instrument is constructed in accordance with the applicable European directives LVD 73 23...

Страница 26: ...d the I O communication to external apparatus see figure x In the table below you can find the detailed list of the terminal numbers and its function Further detailed information of the functions refe...

Страница 27: ...n For factory use only 21 22 Stop calibration 23 24 Failure signal output 25 26 Warning signal output 27 28 Forward flow direction low flow cut off forward 29 30 Reverse flow direction low flow cut of...

Страница 28: ...ith the UFC V Flow Converter unit and is factory set The second channel is defined for Modbus communication with external systems Flow data and relevant auxiliary signals are available A user configur...

Страница 29: ...in line with the following model confirming that the flow meter is safe to handle If the flowmeter has been operated with toxic caustic flammable or water polluting liquids you are kindly requested T...

Страница 30: ...30 www krohne com 04 2012 ALTOSONIC V SERVICING 4 4 2 Spare parts For more information please contact KROHNE...

Страница 31: ...Analysis products Measuring systems for the oil and gas industry Measuring systems for sea going tankers Head Office KROHNE Messtechnik GmbH Ludwig Krohne Str 5 D 47058 Duisburg Germany Tel 49 0 203 3...

Отзывы: