57
Important:
Before continuing any further with the assembly from this point, the scaffold must be
fitted with the ballast weight required depending on the scaffold‘s current height. For
more information on how to use the ballast weights, please refer to pages 66 – 69 of this
Assembly and User Manual.
Note:
In order to assemble and disassemble
the scaffold tower, it is necessary to
build a number of temporary platforms,
which need to be removed again once
the scaffold has been fully erected. In
accordance with DIN 4420-1, these
planks have to have a minimum width
of 24 cm and minimum thickness of
4.5 cm. The planks have to protrude
a minimum of 20 cm over each of the
scaffold‘s sides.
Step 6
Construct a temporary platform using
solid scaffold planks and have another
2 diagonal braces passed to you.
Содержание 731302
Страница 12: ...12 Kennzeichnung Das Typenschild ist an den Vertikalrahmen des STABILO Fahrger st Systems angebracht...
Страница 24: ...24 Die Abbildung zeigt das fertig montierte Ger st fahrbare Arbeitsb hne mit einer Arbeitsh he von 6 40 m...
Страница 62: ...62 The image below shows a fully assembled scaffold tower with a working height of 6 40 metres...