Termination Cap Framing–Roof Termination Framing
SECTION 2
INSTALLATION
5
#HTK-EXT
R.10, October 2021
HUSSONG MFG. CO., INC.
KOZY HEAT FIREPLACES
2.0 INSTALLATION
2.1 Termination Cap Framing
IMPORTANT: Termination framing MUST be level so the termination
cap is level upon installation. This is required so precipitation does not
build up inside the termination cap.
Find the desired location of exterior heat transfer kit termination.
Refer to
for dimensions. For horizontal termination cap
clearances, see
2.2 Roof Termination Framing
If the #HTK-EXT will terminate on a flat roof, construct an enclosure
similar to the one shown in
10”
(254mm)
13
½
”
(343mm)
12”
(305mm)
FIGURE 2.2
Rooftop Enclosure Framing
FIGURE 2.1
Framing Dimensions