– This test takes place with the vessel in open sea. It is performed by the installation
personnel from Kongsberg Maritime together with representatives from the
customer and in some cases the installation shipyard. The purpose of the test is to
check the functional specifications of the system during normal working conditions.
Visual inspection of units
Scope
WARNING
These checks must be completed before any power is switched onto
the system.
After the physical installation has been carried out, all the system units must be visually
checked to ensure that the EM 122 units have been installed correctly. You must ensure
that the units have been mounted in the correct locations, correctly orientated (e.g. the
right way up) and are correctly secured.
Operator Unit
Perform a close visual inspection of the unit according to the following procedure
1
Check that the unit is installed properly, secured, and that it is suitably orientated to
enable easy operation.
2
Check that the unit is not damaged.
3
Make sure that appropriate slack has been applied to the cables.
4
Check that the air vents are not blocked.
5
Check the immediate environment around the unit. The operator should have easy
access to a communication system, and it must be possible to dim and/or switch
off the deckhead lights.
6
Checked (date/sign):__________________________
Transceiver Unit
Perform a close visual inspection of the EM 122 Transceiver Unit cabinet.
1
Check that the unit is installed in the correct location, and is suitably orientated to
enable easy maintenance.
2
Check that the proper mounting bolts have been used, and that proper torque has
been applied.
3
Check that the unit is not damaged.
4
Make sure that you have access to the internal part of the cabinet, from both sides,
and that appropriate slack has been applied to the cables.
5
Check that the air vents are not blocked.
317669/B
103
Содержание EM 122
Страница 1: ...EM 122 Multibeam echo sounder Installation Manual...
Страница 2: ......
Страница 13: ...EM 122 Figure 1 System diagram 317669 B 11...
Страница 26: ...EM 122 Figure 6 EM 122 Gondola example Cd021 107 24 317669 B...
Страница 27: ...Transducer arrays Figure 7 EM 122 blister and steel pipe arrangements example 317669 B 25...
Страница 42: ...EM 122 B B B Plastic TX protection window 40 317669 B...
Страница 46: ...EM 122 Figure 10 EM 122 Transceiver unit mounting 44 317669 B...
Страница 52: ...EM 122 Figure 13 Rear view 50 317669 B...
Страница 54: ...EM 122 Figure 15 Preamplifier Unit mounting 687 52 317669 B...
Страница 60: ...EM 122 Figure 18 Remote Control Junction Box outline dimensions 58 317669 B...
Страница 85: ...Cable layout and interconnections Figure 32 Transceiver Unit sub racks rear view 317669 B 83...
Страница 88: ...EM 122 Figure 34 Preamplifier underneath view 86 317669 B...
Страница 97: ...Cable layout and interconnections Figure 40 EM 122 Transceiver Unit s rear panel RX 317669 B 95...
Страница 126: ...EM 122 Figure 57 Cable layout 0 5 degree TX page 1 of 2 Cd021 106 Page 1 of 2 315396 Pro03 124 317669 B...
Страница 127: ...Drawing file Figure 58 Cable layout 0 5 degree TX page 2 of 2 Cd021 106 Page 2 of 2 315396 Pro03 317669 B 125...
Страница 128: ...EM 122 Ice window Figure 59 TX Ice window 126 317669 B...
Страница 129: ...Drawing file Figure 60 RX Ice window 317669 B 127...
Страница 131: ...Drawing file Preamplifier Unit Figure 62 RX Preamplifier Unit internal cabling 317669 B 129...
Страница 132: ...EM 122 Figure 63 RX Preamplifier Unit internal cabling 130 317669 B...
Страница 154: ...2013 Kongsberg Maritime...