2.5. Menu
Menu of panel consists of the four points:
Functions
Settings
Overview
Scheduling
Menu
ECONOMY 1
21,9 °C
21,3 °C
Temperature
16:30
Alarms
Operation counters
Efficiency status
Detailed information
Overview
2.5.1. Overview
Main air handling unit parameters are presented in
the main windows (Chapter 2.3). All other informa-
tion, relating to the operation of the unit, malfunctions
and efficiency status is detailed in overview menu.
Functions
Settings
Overview
Scheduling
Menu
2.5.1.1. Alarms
This menu displays the notification of existing faults.
After failure elimination (see chapter 2.8), mes-
sages are deleted by selecting “Delete”. By click-
ing on „History“ can be viewed up to 50 registered
alarms.
2.5.1.2. Operation counters
This menu displays operation time of the fans, the
consumed energy of the heater and how much en-
ergy was recovered by the heat exchanger.
2.5.1.3. Efficiency status
Menu for the heat exchanger efficiency and energy
recovery monitoring in real time.
Also in this menu it is possible to start CF ex
-
changer calibration, if it was not performed during
first start of AHU. If calibration was successful and
“Calibrated” is shown – there is no need to start cali-
bration again. During calibration AHU will operate for
about 10 minutes on different ventilation intensities
while measuring internal pressure. Thus do not open
AHU doors, do not regulate duct system and do not
change any settings during CF calibration. If you wish
to stop calibration – turn off the unit from the control
panel.
2.5.1.4. Detailed information
All temperature sensor readings, functioning of sepa-
rate air handling unit elements and other detailed in-
formation is available in this menu.
Operation counters
Air heater
121 kWh
Supply fan
873 h
Exhaust fan
875 h
Recovered energy
1440 kWh
21A
Electric heater overheating
3B
VAV calibration fail
Alarms
Delete
History
Detailed information
Supply air flow
350 m
3
/h
1 / 3
Supply air temperature
21,9 °C
Extract air temperature
22,1 °C
Outdoor air temperature
16,6 °C
Water temperature
25,3 °C
Calibrated
CF exchanger calibration
Efficiency status
83%
Energy saving
90%
Energy recovery
4,1 kW
Heat exchanger efficiency