Continue for all models
Whilst the fire box is still in position, decide which side the gas supply is to enter
the fire from. If concealed pipe work is required plan the pipe run to enter the fire
box through one of the openings in the sides of the fire box below the fuelbed
support panel and connect to the isolating / inlet elbow. The gas connection to the
appliance should be made to the isolating / inlet elbow using 8mm rigid tubing.
There must be no soldered joints within the firebox. See figure 8 & 9 below for
suggested concealed pipe layouts.
Fig. 8
Fig. 9
Note : Before breaking into the gas supply a tightness test should be carried
out to establish that the existing pipework is sound.
Carefully withdraw the fire box from the opening to enable the gas supply and fire
fixing to be completed.
14
Firebox
Fireplace
Builders
Opening
Gas Supply
Firebox
Approx.
40mm
Fireplace
Gas Supply
Approx.
40mm
Builders
Opening
IMPORTANT NOTE : USE THE FOIL TAPE SUPPLIED TO SEAL THE UNUSED
GAS ENTRY POINTS ON THE FIREBOX. BFM EUROPE WILL NOT ACCEPT
GUARANTEE CLAIMS THAT ARE AS RESULT OF THE UNUSED GAS ENTRY
POINTS NOT BEING SEALED.