background image

012696  GL0011P-07 

– Installation Guidelines for BioDisc BA, BAx, BB & NB Units 

    Page  7 

installation is complete. In such conditions it may be advisable to line the excavation with polythene 
sheeting, to prevent cement being washed out of the concrete surround/base.  

2.1.4 

During installation care must be taken to ensure that the body of any unit is uniformly supported so 
that point loads through the unit are avoided. 

2.1.5 

A water supply must be available on site to enable the unit to be ballasted during back-filling. 

2.1.6 

Concrete Specification below is a 

general 

specification. It is not a site specific installation design. 

2.1.7 

A Dry Site

 is defined as one where groundwater lies below the base of the excavation at all times 

and the subsoil is free-

draining. If in any doubt, assume “Wet Site” conditions. 

GENERAL CONCRETE SPECIFICATION  

IN ACCORDANCE WITH  BS EN 206-1 ( BS 8500-1) 

TYPE OF MIX 

(DC)  DESIGN 

PERMITTED TYPE OF CEMENT 

BS 12 (OPC): BS 12 (RHPC): BS 4027 (SRPC) 

PERMITTED 

TYPE 

OF 

AGGREGATE  

(coarse & fine) 

BS 882 

NOMINAL MAXIMUM SIZE OF AGGREGATE 

20 mm 

GRADES:                     C25 /30 
                                     C25 /30  
                                     C16 /20 

REINFORCED  &  ABOVE  GROUND  WITH  HOLDING 
DOWN BOLTS 
REINFORCED (EG. FOR HIGH WATER TABLE) 
UNREINFORCED (NORMAL CONDITIONS) 

MINIMUM 

CEMENT 

CONTENT 

C30 
C20 

270 - 280 Kg/M

3

 

220 - 230 Kg/M

3

 

SLUMP CLASS 

S1 (25mm) 

RATE OF SAMPLING 

READY  MIX  CONCRETE  SHOULD  BE  SUPPLIED 
COMPLETE 

WITH 

APPROPRIATE 

DELIVERY 

TICKET IN ACCORDANCE WITH BS EN 12350-1 

                                       

NOTE:  STANDARD MIXES SHOULD NOT BE USED WHERE SULPHATES 

2.1.8 

                             OR OTHER AGGRESSIVE CHEMICALS EXIST IN GROUND WATER

 

 

2.2 

BioDisc Installation 

2.2.1 

The package tied to the outside of the unit contains this copy of the Installation Guidelines and a 
cover key. 

2.2.2 

Excavate a hole of sufficient length and width to accommodate the unit and a minimum of 150mm 
concrete surround and to a depth which allows for the burial depth of the unit plus a minimum 
150mm thick concrete bed. 

2.2.3 

Lay a concrete bed, of thickness appropriate to site conditions. In wet or unstable ground conditions 
it may be necessary to lay an additional hard-core sub-base (see 1.3.4 & 2.1.3).  

2.2.4 

Lower the unit onto the concrete and bed it in, ensuring that there are no voids under the BioDisc 
base. 

2.2.5 

Unlock and remove the cover. Remove the Control Panel and Owners Pack from inside the unit. 

2.2.6 

Check that the inlet and outlet orientation is correct and that the unit is level. It is essential that the 
unit is installed in a level plane to avoid undue stress on the bearings.  

2.2.7 

The rotor shaft must be level end to end, to within ±3mm, measured at the bearing caps or directly 
on the shaft. 

2.2.8 

The unit must also be level to within ±5mm from side to side, measured at the GRP walkway on 
either side of the rotor. 

2.2.9 

If necessary, lift the unit off the base and apply further concrete as needed to level up. 

2.2.10  Note : The top flange of the BioDisc should not be used for levelling as manufacturing tolerances 

may result in it not being parallel with the rotor shaft. 

2.2.11  Haunch up concrete all round the base of the unit to at least 150mm above the base level. 

2.2.12  Pour water into the primary (inlet) chamber and the final (outlet) chamber, to a depth of 200mm. 

2.2.13  Back-fill according to site conditions (see 2.1.7) 

2.2.14 

Note: 1250mm inlet invert depth units must be back-filled with concrete to within 500mm of 
ground level as a minimum, irrespective of site conditions. 

Содержание BioDisc BA

Страница 1: ...ical connection or if there is no power available to operate the unit then the motor with gearbox must be removed and stored in a dry environment The motor keeps dry by generating its own heat when op...

Страница 2: ...d recommended Please contact Kingspan for details of your local service provider Should you wish to inspect the operation of the equipment please observe all necessary precautions including those list...

Страница 3: ...shire HP22 5EW United Kingdom 07 EN 12566 3 BA BF BioDisc Hydraulic daily load 1 2m day 10m day Material GRP Glass Reinforced Plastic Watertightness water test Pass Structural Calculation Pass Treatme...

Страница 4: ...4 2 Mounting Frame Installation where applicable 10 4 3 Installation of Control Panel 10 4 4 Installation of Integral Discharge Pump where applicable 11 4 5 Installation of Sludge Return Pump where ap...

Страница 5: ...owing points should be considered before installation of the equipment 1 3 2 The discharge must have the consent of the relevant Environmental Regulator 1 3 3 The installation should have Planning and...

Страница 6: ...table selection of the cable is the responsibility of the installing electrician Full Load Current Amps BA BAx BB NB Motor 240 volt single phase 0 52 0 52 0 52 0 52 415 volt three phase 0 22 0 22 0 22...

Страница 7: ...of the unit contains this copy of the Installation Guidelines and a cover key 2 2 2 Excavate a hole of sufficient length and width to accommodate the unit and a minimum of 150mm concrete surround and...

Страница 8: ...red Cable supply to control panel Customer Supply Inlet Pipe Outlet Effluent to Soakaway Ditch Stream etc via Sample Chamber if fitted Control Panel Refer to Section 6 for position G L 450mm Inlet Inv...

Страница 9: ...l as described in Section 3 2 4 6 Continue to back fill with concrete wet site or free flowing granular material dry site up to ground level The finished surface should be 95 mm minimum lower than the...

Страница 10: ...et 4 2 2 Allow 350mm minimum clearance from finished ground level to the bottom of the panel 4 3 Installation of Control Panel Figure 1 Control Panel 4 3 1 Remove the four screws on the front of the p...

Страница 11: ...applicable 4 5 1 Using a suitable M20 gland feed the integral discharge pump power cable through Gland Hole 3 Figure 1 and terminate to connection 3 4 TB2 following the guide on Table 2 4 5 2 Set the...

Страница 12: ...crewdriver push switch 10 to the ON position 4 8 Installation of High Level Alarm where applicable 4 8 1 Remove the link in the terminal blocks between connections 11 12 TB6 before inserting cables Us...

Страница 13: ...owing the procedure in the Owners Handbook and leave the unit running even if there is no sewage being fed into the plant 7 1 4 If the unit has been installed with no operational power supply then rem...

Отзывы: