5.3 Functional check
Preparation
▶ Fill wastewater tank with water.
▶ If necessary, switch the control unit on.
▶ Deactivate the automatic mode (
| 2.1 Automatic mode |
).
2 testing procedures are carried out for the functional
check.
1. Check the alarm level
2. Check the pump(s)
Check the alarm level
1
If necessary, switch the control unit on.
▶ Fill the wastewater tank with water, but let the level rise until the control
unit triggers an alarm (acoustic signal is heard / alarm LED flashes).
▶ Switch off water feed.
Check the pump(s)
1
Activate the pump(s) by manual control using the button [17-2] and/or[17-3].
The button has to be pressed twice to activate the pump.
▶ Run the pump(s) until the level falls below the alarm level again.
▶ The alarm message can be acknowledged with the button [17-1] on the
control unit.
▶ Reactivate the automatic mode (
| 2.1 Automatic mode |)
.
✓
The system is ready for operation
[17]