4. Fan installation procedures
1
Preparation
2
confirmation
3
Inspection
4
Top plate
5
Extension rod
6
Safety rope
7
power cable
Notice: When unloading product should put down gently when unloading,
product’s position should not affect the field production and channel.
Notice: Carefully confirm the following information 1, Installation point 2, installation
height 3, whether there are obstacles (such as crane, light, Cable, fire protection,
cameras) 4, control cabinet position 5, the input power and the power cord layout, 6,
power line layout, 7, traction steel wire position.
Notice: Check the security measures (such as seat belts, helmets, etc.), climbing
equipment, tools, products and accessories.
Notice: the extension tube is 90 degrees measured with a gradienter.
Notice: keep the surface of the cable good and 20cm out of the tube is ok after
threading.
Notice: Both sides of the top plate is same and isometric, top plate must be vertical to
the H-beam and the shim need to be close to H-beam, clamping pieces are fully
combined with the beam. Other installation types should reach the same standard.
Extension rod
Pressure plate
fastener
Steel structure
-10-
INSTALLATION GUIDE
BOREAS