8
Commissioning
8.1
Requirements
DANGER
Lethal voltages are still present in the connections and cables of the device even after the device
has been switched off and disconnected!
Severe injuries or death may occur if the cables and/or terminals/busbars in the device are touched.
1. The device is only permitted to be commissioned by a qualified professional.
2. Unauthorised persons must be kept away from the device.
↻
The device has been mounted and electrically installed.
↻
The PV generator supplies a voltage above the configured start voltage.
1. Connect the grid voltage using the external circuit breakers.
2. Connect the PV generator using the DC isolator switch (0 > 1)
ð
The device begins operation.
ð
During initial start-up: Follow the instructions of the New Connection Wizard.
NOTE
A mobile terminal device with WIFI interface is required in order to put the device into operation.
The following functions are only available via the WEB interface:
1. Initial start-up
2. Setting parameters
3. Resetting the device to its factory defaults
NOTE
We recommend using an up-to-date Firefox or Chrome browser or the default browser that is available on the
mobile terminal devices to configure the device via the web interface.
8 | Commissioning
Manual
KACO blueplanet 100 TL3
Page 32
EN