4.2
Operation
4.2.1
Commissioning unfilled batteries
Z
The operations required must be carried out by the manufacturer's customer service
department or a customer service organisation authorised by the manufacturer.
4.2.2
Commissioning filled and charged batteries
Battery cell cross section
Top view of a battery cell
107
108
109
107
108
109
Checks and operations to be performed before starting daily work
Procedure
• Make sure the battery is in physically good condition.
• Make sure the terminals are correct (positive to positive and negative to negative)
and check that contacts on the battery terminal conducting system are secure.
• Check the M10 terminal screws of the conductors and connectors are secure and
if necessary torque to 23 ±1 Nm.
• Charge the battery, see page 154.
• Check the electrolyte level of each battery cell after charging and top up if
necessary:
• Open the plug (107).
Z
The electrolyte level should not be less than the "Min" electrolyte marking (108)
and must not exceed the "Max" (109) marking.
• If necessary, add electrolyte with pure water up to the "Max" electrolyte level
marking (109), see page 156.
• Close the plug (107).
The test is now complete.
153
04.19 en-GB
Содержание ESE 220
Страница 1: ...ESE 220 320 03 10 Operating instructions 51163703 04 19 en GB ESE 220 ESE 320...
Страница 2: ...2...
Страница 4: ...4 04 19 en GB...
Страница 10: ...10 04 19 en GB...
Страница 14: ...14 04 19 en GB...
Страница 49: ...2 Displays and Controls 5 7 10 49 50 51 52 53 11 14 13 54 55 56 17 49 04 19 en GB...
Страница 70: ...17 10 70 04 19 en GB...
Страница 79: ...The brake is now released The truck can be moved 79 04 19 en GB...
Страница 148: ...148 04 19 en GB...