210.100-IOM (JUL 2021)
Page 36
AcuAir Hygienic Air Units
Installation
5.
After the latches have been installed, configure the
frame as shown in the following
Figure
.
Figure 44: Frame with 4 latches
NOTICE
The frame contains two latches each side, none on
the top or bottom.
6.
Insert the rigid DH filter into the frame. While holding
the filter in the frame, grasp the loop on the end of the
latch and pull it until it stretches over the header and
rests into the pre-drilled hole in the header of the filter
). Repeat this with the remaining latches.
7.
Ensure the filter is securely installed into the frame.
Figure 45: Pull and fasten the spring latch in hole in the
header of the filter
CAUTION
Take care to prevent contamination of the filter me
-
dia before placement in the filter racks. Never place
fresh filters on dirty surfaces such as roofs or floors.
CAUTION
Pleated filters must be installed with the pleats run
-
ning vertical whenever possible.