5.3 Suggestion for preservation specification & record:
PRESERVATION SPECIFICATION & RECORD
Record No.:
Tag No.:
Description:
Record page 1 of 1
Activity
No.:
Intervals
(Months)
Description of
Preservation Ac-
tivity
Recom-
mended Pre-
servative
Initial
Preservation
Date/Sign
Pre-
served (2)
Date/Sign
Preserved
(3)
Date/Sign
Pre-
served (4)
Date/Sign
Pre-
served (5)
1
1
Check that protec-
tion structure is un-
damaged.
2
6
The desiccant bag
inside the Junction
boxes replaced.
3
1
Check the storage
conditions.
Relative humidity <
= 60 %, temp. > =
15˚C
4
12
If stored for more
than one year from
packing date, the
supplier must be
contacted for ad-
vice regarding re-
newal of the desic-
cant bag.
5
12
Check the paint-
work.
6
12
Check that there is
no visual damage
to the equipment.
7
12
Verify that the gen-
eral condition of the
equipment is satis-
factory.
8
12
All openings such
as cable entry
holes are ade-
quately sealed.
Junction Boxes as
well.
9
12
All loose items/re-
moved parts pre-
served, stored and
marked.
10
6
Verify no water
leakages, conden-
sation or moisture
where applicable.
11
6
The Anti-condensa-
tion heater in the
equipment must be
powered up and
connected at all
times.
Comments:
Performed by:
Date/Sign:
Accepted by:
Date/Sign: