background image

Fig. 15

A minimum 75mm thick Floor protector is only required if finished surface is combustible e.g: timber, carpet, tiles

Please note that these dimensions (based on Masonry margins) are the absolute minimum sizes - widths (A & B)

maybe increased if desired. If you intend on recessing the firebox, please add the recess value to Dimension ‘B’.

WARNING: Minimum cavity sizes leave NO MARGIN FOR ERROR . If the cavity is larger than minimum 

dimensions (A & B) close up the lateral sides using hebel block, concrete block or similar (do not use any 

combustible material).

Refer to Table 3 for the minimum cavity dimensions and temporary lintel height measurements, until the firebox and 

flue system is installed. Note: Temporary lintel height is measured from finished floor protector level.

Ensure suitable air vents (min. 2 x 80mm diameter or equivalent) in place to vent firebox space - these maybe located

in the floor or in the side wall space; make allowance (min. 2 x 80mm diameter or equivalent) at the top of the chimney

chase, Pg. 14. Ensure vents are bird and vermin proofed.

CROSS SECTION

CAVITY PREPARATION

6.TMWG.10

Dra

wi

ng

N

ot

To

Scal

e

Flue pipe casing 

recommended

SS Flue pipe

Rock-wool 

insulation

min 2 x 100 x 50mm 

or 80mm diam. wall 

or

floor

mounted air 

vents

min

Refer to Table 2 for

floor

protector dimension

if

floor

is made of combustible material

Concrete Lintel or 

Hebel Block (lintel bar

may be required)

Lintel Bar
Rock-wool 

insulation
Allow 2mm 

clearance for 

expansion

Ensure the

air intake is 

unobstructed

100

B + recessed

Allow 5mm gap

around all four 

sides of the firebox 

to fit Stainless

Steel cover & allow

for firebox 

expansion

RECESSED

REQUIRED 40mm Min.

- 100mm Max recess

Allow 5mm gap between plaster and flange to

ensure stainless steel cover can be fitted to the 

box.

DO NOT PLASTER OVER THE FLANGE.

Jetmaster

Flange

All external air vents & ceiling penetrations must be

bird & rodent proofed with permanently

fixed screen

Fig. 17

Fig. 16

If recessing allow 2

mm for expansion of

the firebox

Don’t plaster over the flange

Содержание 700

Страница 1: ...warranty Due to continued product improvement The Fireplace Ltd reserves the right to change product specifications without prior notification Please check to ensure you have the latest installation...

Страница 2: ...hield Firebox Installation Gas Requirements Plan Section Drawing Plan Section Recessed Drawing Masonry Cavity Dimensions Solid Fuel Flue Installation Gas Flue Installation Flue Penetration Chimney Cha...

Страница 3: ...IN HEATER INSTALLATION CLEARANCES WHEN OPERATING THIS APPLIANCE AS AN OPEN FIRE USE A FIRE SCREEN THIS APPLIANCE SHOULD BE MAINTAINED AND OPERATED AT ALL TIMES IN ACCORDANCE WITH THESE INSTRUCTIONS US...

Страница 4: ...ather available 1050IGC Box is ONLY for gas installations MODEL A A1 A2 B C D E F Y Off set Gather Indoor Gas Burner 700 700 800 750 400 700 225 325 200 680 295 395 Yes 850 850 950 900 450 700 250 350...

Страница 5: ...ensure allowance is made to place non combustible internal wall lining eg Promatect H to cover the extent of the Hebel panel surround shown shaded Directly touching the firebox with any board or plas...

Страница 6: ...r entry between the inner flue pipe and flue pipe casing or the air circulation between the vent holes in the cavity 7 Once the flue system is installed place a minimum 300mm hebel block over the top...

Страница 7: ...ns must be bird rodent proofed with permanently fixed screens Gib Board Hebel Block Non combustible material eg Promatect H Lintel Bar Rock Wool insulation see Table 2 Secure the firebox with 2 x 12mm...

Страница 8: ...x with 2 x12mm dynabolts for earthquake retraints Maintain the air intake unobstructed Floor Protector Fig 10 Fig 11 B see Table 2 Note All external air vents ceiling penetrations must be bird rodent...

Страница 9: ...Floor Protector dimension RECESS REQUIRED 40mm Min 100mm Max Allow gas line into firebox if applicable Air Vent Y Refer toTable 2 for Floor Protector dimension Air Vent min 2 x 100 x 50mm or 80mm diam...

Страница 10: ...side wall space make allowance min 2 x 80mm diameter or equivalent at the top of the chimney chase Pg 14 Ensure vents are bird and vermin proofed CROSS SECTION CAVITY PREPARATION 6 TMWG 10 Drawing No...

Страница 11: ...pipe to be connected to the burner 2 Location of the hole should align with the gap between the gas grate s supporting legs 3 The gas supply pipe enters the firebox above the base plate to terminate u...

Страница 12: ...ver spigot when fitted sizing measuring and cutting down should be carried out prior to the flue pipe casing being fitted over the flue pipe 2 Before fitting casing cover place the spider in oppositio...

Страница 13: ...out prior to the flue pipe casing being fitted over the flue pipe 7 Before fitting casing cover place the spider in opposition with the spider post facing down between the flue pipe and flue pipe casi...

Страница 14: ...r rectangle shaped area min 25mm gap between flue pipe casing combustible surface EXTERNAL REQUIREMENTS SOLID FUEL Refer to AS NZS2918 2001 4 9 1 Note All external air vents ceiling penetrations must...

Страница 15: ...75 850 250 350 400 400 1050 IGC 250 300 350 350 1050 300 400 450 450 1200 400 500 550 550 1500 450 550 600 600 Table 4 CHIMNEY CHASE MINIMUM TRIM OUT 6 TMWG 15 MODEL A B C GAS B 700 1100 400 75 8 300...

Страница 16: ...fer below for air vent sizing and suggested location Fig 26 Location points A B C D are suggested combinations A minimum of one pair of air vents is recommended or one large vent as per location point...

Страница 17: ...tructed of combustible material it must be located within the shaded area defined in Fig 28 Fig 28 Projection mm Combustible Materials Non Combustible Materials CLEARANCE TO COMBUSTIBLE MANTELS 6 TMWG...

Отзывы: