Introduction

It is the responsibility of the competent people that

plan the work and operate the machine to make a

judgement about the safe use of the machine, they

must take into account the specific application and

conditions of use at the time.

It is essential that a risk assessment of the work to be

done is completed and that the operator obeys any

safety precautions that the assessment identifies.

If you are unsure of the suitability of the machine for

a specific task, contact your JCB dealer who will be

pleased to advise you.

The  following  considerations  are  intended  as

suggestions of some of the factors to be taken into

account  when  a  risk  assessment  is  made.  Other

factors may need to be considered.

A good risk assessment depends on the training and

experience of the operator. Do not put your life or the

lives of others at risk.

Personnel

Are  all  persons  who  will  take  part  in  the

operation sufficiently trained, experienced and

competent? Are they fit and sufficiently rested?

A sick or tired operator is a dangerous operator.

Is  supervision  needed?  Is  the  supervisor

sufficiently trained and experienced?

As  well  as  the  machine  operator,  are  any

assistants or lookouts needed?

The Machine

Is it in good working order?

Have any reported defects been corrected?

Have the daily checks been carried out?

Are the tyres still  at the  correct  pressure and

in good condition and is there sufficient fuel to

complete the job (if applicable)?

The Load

How heavy is it? Is it within the capabilities of

the machine?

How bulky is it? The greater the surface area,

the more affected it will be by wind speeds.

Is  it  an  awkward  shape?  How  is  the  weight

distributed? Uneven loads are more difficult to

handle.

Is there a possibility of the load shifting while

being moved?

Loading/Unloading Area

Is it level? Any slope of more than 2.5% (1 in

40) must be carefully considered.

Is more than one direction of approach to the

load  possible?  Approaching  across  the  slope

must be avoided, if possible.

Is the ground solid? Will it support the weight of

the machine when loaded?

How  rough  is  the  ground?  Are  there  any

sharp projections which could cause damage,

particularly to the tyres?

Are there any obstacles or hazards in the area,

for  example,  debris,  excavations,  manhole

covers, power lines?

Is the space sufficient for safe manoeuvring?

Are any other machines or persons likely to be

in or to enter the area while operations are in

progress?

The Route to be Travelled

How solid is the ground, will it provide sufficient

traction and braking? Soft ground will affect the

stability of the machine and this must be taken

into account.

How  steep  are  any  slopes,  up/down/across?

A  cross  slope  is  particularly  hazardous,  is  it

possible to detour to avoid them?

Weather

How windy is it? High wind will adversely affect

the stability of a loaded machine, particularly if

the load is bulky.

Is  it  raining  or  is  rain  likely?  The  ground  that

was  solid  and  smooth  when  dry  will  become

uneven and slippery when wet, and it will not

give the same conditions for traction, steering

or braking.

Содержание 67C-1

Страница 1: ...Operator s Manual You must understand and follow the instructions in the Operator s Manual If you do not understand anything ask your employer or JCB dealer to explain it Do not operate the machine wi...

Страница 2: ...9813 3450 2 Notes Find manuals at https best manuals com...

Страница 3: ...3450 2 SERVICE MANUAL Volume 1 67C 1 EN 9813 3450 SERVICE MANUAL Volume 2 67C 1 EN 9813 3450 SERVICE MANUAL Volume 3 67C 1 EN 9813 3450 SERVICE MANUAL Volume 4 67C 1 EN 9813 3450 Find manuals at https...

Страница 4: ...Notes 9813 3450 2 Find manuals at https best manuals com...

Страница 5: ...ety 01 6 01 03 18 Operating Safety 01 8 01 03 21 Worksite Safety 01 10 01 03 24 Risk Assessment 01 11 01 03 27 Maintenance Positions 01 12 01 06 About this Manual 01 06 03 Model and Serial Number 01 1...

Страница 6: ...9813 3450 2 2018 02 05 Acronyms Glossary PIL Parts Identification List Find manuals at https best manuals com...

Страница 7: ...y Yours and Others 01 3 01 03 06 Safety Warnings 01 4 01 03 09 General Safety 01 5 01 03 12 Maintenance Safety 01 6 01 03 18 Operating Safety 01 8 01 03 21 Worksite Safety 01 10 01 03 24 Risk Assessme...

Страница 8: ...Notes 01 2 9813 3450 2 01 2 Find manuals at https best manuals com...

Страница 9: ...ial hazards and how to avoid them If you do not fully understand the warning messages ask your employer or JCB dealer to explain them Safety is not just a matter of responding to the warnings All the...

Страница 10: ...dous situation which if not avoided could result in death or serious injury The signal word CAUTION indicates a hazardous situation which if not avoided could result in minor or moderate injury The si...

Страница 11: ...e of medicines which can cause drowsiness Feeling Unwell Do not attempt to operate the machine if you are feeling unwell By doing so you could be a danger to yourself and those you work with Mobile Ph...

Страница 12: ...lic Pressure Hydraulic fluid at system pressure can injure you Before connecting or removing any hydraulic hose residual hydraulic pressure trapped in the service hose line must be vented Make sure th...

Страница 13: ...composition e g charring is found refer to the next paragraph for safety instructions Do not touch component or surrounding area Used fluoroelastomeric components subjected to temperatures greater tha...

Страница 14: ...y kill you or bystanders if they are inhaled Do not operate the machine in closed spaces without making sure there is good ventilation If possible install an exhaust extractor If you begin to feel dro...

Страница 15: ...ee clearly Modification of the machine s configuration by the user e g the fitting of large and non approved attachments may result in a restriction of the machine visibility Hands and Feet Keep your...

Страница 16: ...leak is suspected contact the local gas company immediately and warn all personnel on the site Ban smoking make sure that all naked lights are extinguished and switch off any engines which may be runn...

Страница 17: ...nd is there sufficient fuel to complete the job if applicable The Load How heavy is it Is it within the capabilities of the machine How bulky is it The greater the surface area the more affected it wi...

Страница 18: ...is feature must only be used by trained personnel Refer to PIL 09 00 00 Excavator Arm Lowered 1 Park the machine on solid level ground 1 1 Release the two track levers 1 2 Push the hand throttle lever...

Страница 19: ...on solid level ground To prevent anyone starting the engine remove the ignition key Disconnect the battery by means of the battery isolator if installed when you are not using electrical power If you...

Страница 20: ...01 Machine 06 About this Manual 01 14 9813 3450 2 01 14 06 About this Manual Contents Page No 01 06 03 Model and Serial Number 01 15 01 06 06 Using the Manual 01 16...

Страница 21: ...his Manual 03 Model and Serial Number 01 15 9813 3450 2 01 15 03 Model and Serial Number Introduction This manual provides information for the following model s in the JCB machine range Model From To...

Страница 22: ...information is for which variant Make sure you use the correct information Diagnostics Information in this manual can help you diagnose machine faults Before attempting to diagnose possible faults ch...

Страница 23: ...01 Machine 09 Description 01 17 9813 3450 2 01 17 09 Description Contents Page No 01 09 12 Main Component Locations 01 19 01 09 15 Service Point Locations 01 20...

Страница 24: ...Notes 01 18 9813 3450 2 01 18...

Страница 25: ...19 9813 3450 2 01 19 12 Main Component Locations Component Identification Figure 3 A B C D E F G A Dipper part of the excavator arm B Boom part of the excavator arm C Cab contains the operator station...

Страница 26: ...ocations Introduction The following illustrations identify the service points for the operator to perform the daily and weekly maintenance tasks Hydraulic Compartment Figure 4 B C D E A A Fuel filter...

Страница 27: ...ervice Point Locations 01 21 9813 3450 2 01 21 Engine Compartment Figure 5 G F E D C H A B A Air filter B Coolant expansion bottle C Battery D Battery isolator E Radiator F Washer bottle G Engine oil...

Страница 28: ...01 Machine 33 Cleaning 01 22 9813 3450 2 01 22 33 Cleaning Contents Page No 01 33 00 General 01 23...

Страница 29: ...ender the machine inoperable Remove dirt using a brush or damp cloth Clean the product with water and or steam Do not let mud debris etc to collect on the product Before you do any service procedures...

Страница 30: ...aim the water jet directly at bearings oil seals or the engine air induction system Use a low pressure water jet and brush to remove dried mud or dirt Use a pressure washer to remove soft dirt and oi...

Страница 31: ...Contents Page No Acronyms Glossary 03 2 03 00 Attachments 03 00 00 General 03 3 03 10 Excavator End Quickhitch 03 10 00 General 03 7 03 10 06 Hydraulic Quickhitch 03 8 03 27 Bucket 03 27 00 General 03...

Страница 32: ...9813 3450 2 2018 02 07 Acronyms Glossary PMV Pressure Maintenance Valve...

Страница 33: ...03 Attachments Couplings and Load Handling 00 Attachments 03 1 9813 3450 2 03 1 00 Attachments Contents Page No 03 00 00 General 03 3...

Страница 34: ...Notes 03 2 9813 3450 2 03 2...

Страница 35: ...ients on which it is safe to operate or the safe distance from power lines Practice using attachments off the job before working with them for the first time JCB attachments are designed and manufactu...

Страница 36: ...r s Manual do not install it use it or remove it until you have obtained read and understood the pertinent information Install attachments only on the machines for which they were designed WARNING Loa...

Страница 37: ...03 Attachments Couplings and Load Handling 10 Excavator End Quickhitch 03 5 9813 3450 2 03 5 10 Excavator End Quickhitch Contents Page No 03 10 00 General 03 7 03 10 06 Hydraulic Quickhitch 03 8...

Страница 38: ...Notes 03 6 9813 3450 2 03 6...

Страница 39: ...change of buckets and attachments on the machine Quickhitches do not normally have a specific function themselves in that they do not carry out handling or digging operations but when installed on a...

Страница 40: ...3 8 9813 3450 2 03 8 06 Hydraulic Quickhitch Technical Data 03 8 Diagram 03 9 Technical Data Table 3 Quickhitch Hydraulic Pressure Low Pressure Quick hitch 32 bar 463 8 psi High Pressure Quick hitch 2...

Страница 41: ...hitch 06 Hydraulic Quickhitch 03 9 9813 3450 2 03 9 Diagram Figure 6 Low Pressure Quickhitch 1 2 3 1 PMV Pressure Maintenance Valve 2 Quickhitch valve 3 Quickhitch Figure 7 High Pressure Quickhitch 1...

Страница 42: ...03 Attachments Couplings and Load Handling 27 Bucket 03 10 9813 3450 2 03 10 27 Bucket Contents Page No 03 27 00 General 03 11 03 27 90 Teeth 03 14...

Страница 43: ...ion A bucket can be installed on many different types of excavating machines The bucket can be directly mounted on to an excavator arm assembly or mounted to the excavator arm via a quickhitch assembl...

Страница 44: ...mised then select a smaller bucket or reposition the machine Remove and Install CAUTION Stand clear and to one side of the bucket while you remove the pivot pins With the pins removed the bucket could...

Страница 45: ...se a suitable lifting device to position the bucket flat on level ground 2 Reverse the machine while aligning the dipper end with the bucket tipping lever 3 Carefully operate the excavator controls to...

Страница 46: ...0 2 03 14 90 Teeth Introduction 03 14 Remove and Install 03 15 Introduction Excavator buckets generally have teeth protruding from the cutting edge to disrupt hard material and avoid wear and tear of...

Страница 47: ...fe Refer to PIL 01 03 2 Put the bucket flat on level ground 3 Stop the engine 4 Remove the ignition key 5 Discharge the hydraulic pressure Refer to PIL 30 00 00 6 Remove the nut and bolt 7 Remove the...

Страница 48: ...03 Attachments Couplings and Load Handling 48 Rockbreaker 03 16 9813 3450 2 03 16 48 Rockbreaker Contents Page No 03 48 00 General 03 17...

Страница 49: ...y 03 18 Remove and Install 03 18 Introduction A hydraulic rockbreaker also called hammer breaker pecker hoe ram or hoe rammer is a powerful attachment installed to the excavator for demolishing concre...

Страница 50: ...rs could be killed or seriously injured Remove and Install To prevent premature wear failure and breakage the Quickhitch assembly must be used with a rockbreaker for short periods only If the machine...

Страница 51: ...This as a preview PDF file from best manuals com Download full PDF manual at best manuals com...

Отзывы: