7. Select the power supply inlet you want to use (Figure A). Feed
power cable to control box, then install it through the large opening
provided in the bottom side of the box.
8. Connect wires, color to color, on terminal blocks TB1 and TB3
(Figure C, page 12). TIGHTEN SECURELY! All wires must be
hooked up securely or damage could result.
9. Install control box door and screws and reinstall the cabinet side
panels.
Congratulations! You are now all set to get your new spa ready to use.
Simply follow this step-by-step procedure below, before long, you will be
enjoying your first glorious experience in your Jacuzzi J-200 spa.
Figure-B - Control Box
1. T
erminal Block
2.
Bonding Lug
3.
Grounding
Terminal
TB1
3
2
1
7
8
3
6
2
2
Figure-A
Equipment Area
1.
Control Box
2.
Power Supply Inlet(s)
3.
2-Speed Pump #1
4.
Heater
5.
Pump Drain Plug
Flow
Note: Pump Locations Vary by Model
5
5
1
4
6.
1-Speed Pump #2
7.
Optional CD Ozonator (Purchased Separately)
8.
Ozone Injector
9.
Control Panel