5.
Remove items #371G and #357A and position lift cable loop between lifting brackets. Apply Loctite
271 and reinsert item #371G, hex head cap screw, through cable and lifting brackets and thread
heavy hex nut, item #357A, and item #415A, jam nut, onto item #371G. Check cable clamps..
3.5.4 Install the slide rail
Refer to drawing B1-445153SLR and B2-445153SLR
1.
With anchor bolts in position, lower the base, item #787A, onto a flat, clean foundation and tighten
anchor bolt nuts.
2.
Insert the slide rails, items #787C over the cylinders on the base and insert intermediate bracket,
item #787P, cylinders into the tops of the slide rails. Allow .25" gap between the top of the slide rails
and the intermediate bracket for thermal expansion. Secure the intermediate bracket to the sump
wall. Repeat as necessary with the remainder of the rails and brackets.
3.
Install the discharge pipe.
4.
Lift the pump using the lift cable and lower it to have the guide bracket fit between the rail pipes.
The pump should be reasonably level to keep the guide bracket from exerting too much force on
the rail pipes when the pump is lowered or raised
5.
Carefully lower the pump into position. Turn the adjusting bolts, items #787J, to provide the proper
o-ring compression. The pump may need to be raised and lowered back into position a few times
until the proper adjustment is found. The pump should properly lock into place with no visible gap
between the o-ring and sump flange adapter. Tighten items #357, hex nuts, against items #787H,
adjusting brackets, to prevent movement of adjusting bolts.
3.5 Slide rail system (optional)
14
JCU Installation, Operation, and Maintenance Manual
Содержание GOULDS PUMPS JCU
Страница 1: ...Installation Operation and Maintenance Manual JCU ...
Страница 2: ......