Fig.  20-Guic/ing  SHV-350  Breaker 

into  Housing 

INSTALLATION  OF  SHV-350  CIRCUIT 
BREAKER 

1. 

The  breaker  should  be  in  the  "OPEN"  posi­

tion  and  the  position  indicator  at  the  "TEST" 

position. 

2. 

By  use  of the  steering handle,  align  the sides 

of  the  circuit  breaker  with  the  sides  of  the  circuit 

breaker  compartment. 

3. 

Back  the  breaker  into  the  compartment  so 

that  the  guide  bar  at  the  bottom  of  the  circuit 

breaker  enters  the  guide  slot  on  the  compartment 

floor.  See  Fig. 

20. 

4. 

Push the  breaker  approximately  half way into 

the  compartment  and  then  remove  the  steering 

handle. 

5. 

Using  the  two  handles  on  the  lower  front 

panel,  continue  pushing  the  breaker  until  the 
rollers  on  the  racking  mechanism  cranks  snap  up 

into the vertical guides in the structure.  The circuit 

breaker  is  now  latched  in  the  "TEST"  position. 

6. 

If  desired,  energize  the  control  circuit  and 

electrically  close  and  trip  the  circuit  breaker  by 
means  of  the  push  buttons. 

7. 

With  the  circuit  breaker  in  the  "OPEN" 

position,  insert the  racking  rod,  push  down  on  the 

racking  release  lever,  and  rack  the  breaker  to  the 

"OPERATING"  position as shown  in Fig. 

21. 

IB-5909 

Fig.  21-Raclcing  in  SHV-350 Breaker 

to 

Fully Connected Position 

REMOVING  5HV -350  BREAKER  FROM 

HOUSING 

1. 

Trip  the  breaker  by  means  of  the  control 

switch. 

2. 

Open the compartment  door,  insert  the  rack­

ing  rod,  push  down  on  the  racking  release  lever 

and  rack  the  circuit  breaker  out  to  the 

'rEST" 

position  as indicated  by the  position 

indicator. 

If it is desired to remove the circuit breaker from 

the  switchboard,  continue  as  follows: 

3. 

Insert  the  racking  rod  into  the  hole  in  the 

racking 

wheel 

directly above  the  "TEST"  position 

nameplate. 

4. 

Push  down  on  the  racking  release  lever,  and 

move  the  racking  rod  slightly 

(15 

degrees)  in  the 

"IN"  direction. 

5. 

Release  the  racking  release lever,  and  move 

the  racking  rod  in  the  direction  of  the  "OUT" 
arrow  {upward)  approxima.tely 

30 

degrees.  This 

upward  motion  of  the  racking  rod  must  be  fast 
enough  to  move  the  circuit  breaker  forward  past 

the  self-latching  "TEST"  position. 

6. 

Remove  the  racking  rod  and  pull 

the 

circuit 

breaker  forward,  using  the  two  handles  on  the 

,. 

· 

lower  front  panel,  until  the  circuit  breaker 

is 

·  · 

approximately  half  way  out of the  compartment. 

't 

• 

www 

. ElectricalPartManuals 

. com 

Содержание 5HV-150

Страница 1: ...PE 5HV 75 5HV 150 5HV 250 AND 5HV 350 METAL CLAD SWITCHGEAR 1 t i t I 5000 VOLT 1200 2000 AND 3000 AMPERE i 1 i x rt i y t l l 1 T E CIRCUIT BREAKER COMPANY PHILADELPHIA 30 PENNSYLVANIA PRINTED IN U S A 7 59 2M w w w E l e c t r i c a l P a r t M a n u a l s c o m ...

Страница 2: ... Inspection 7 STANDARD CONSTRUCTION Shutters 7 Bus Insulation 8 Primary Disconnecting Device 8 Secondary Disconnecting Devices 8 Ground Bus and Contacts 9 Control Wires 9 5HV 75 5HV 150 AND 5HV 250 CIRCUIT BREAKERS General 9 Installation and Removing from Housing 10 SHV 350 CIRCUIT BREAKER Installation and Removing from Housing 13 HOW TO PUT THE SWITCHGEAR IN SERVICE General 14 Safety Precautions ...

Страница 3: ... once The 1 T E Circuit Breaker Company is not re sponsible for damage after delivery of shipment to the carrier However if the company is notified of such claims it will furnish forms to facilitate securing any adjustments If damage to the ship ment indicates rough handling claim for damage should be filed at once with the carrier and the I T E Circuit Breaker Company promptly notified The switch...

Страница 4: ... Switchgear Raised Rollers and Channels in Place Prior to Lateral Moving Fig 2 Switchgear Lowered on Rollers Prior to Moving Onto Track Timber Fig 4 Method oF Applying Rollers as Switchgear Progresses Onto Track Timber Fig 6 Jaclcs Removed and Switchgear Ready For Lateral Moving V _ ii J ff jFfft tl _ w w w E l e c t r i c a l P a r t M a n u a l s c o m ...

Страница 5: ... the lower flange of the sill be shimmed to proper height Temporary bolts should be inserted in all tapped holes while grouting to prevent filling or damage to the threads Where necessary power and secondary con trol conduits should be installed before the in stallation of the housings Available space for the conduits is given on the floor plan accompanying each order These conduits should not ext...

Страница 6: ...f the pothead with wiping sleeve the lead sheath should extend into the pot head for one inch minimum bell over the end of 6 the sheath and add a stress relief cone if required Clean the sheath about three inches beyond the end of the cone and apply stearine flux to end of the cone and the sheatlt Wipe the joint in the usual manner On inverted potheads the lead sheath should be extended down into ...

Страница 7: ...AS POTENTIAL IB 5909 TRANSFORMERS ARE CONNECTED DURING THE TESTS 4 Check continuity of all circuits A great deal of this work can be done after the circuit breakers are installed by energizing the control source and operating the equipment with the main circuit dead Indicating instruments check the continuity of current transformer and potential transformer circuits after the main circuit is energ...

Страница 8: ...ing Device fingers tends to increase the contact pressure dur ing a short circuit All contact finger springs are outside the current path The stationary disconnecting device is rigidly mounted in an insulating molding of cylindrical shape located within the main bus housing See Fig 8 For the SHV 350 housing the disconnecting device is similar but mounted in a molding of rectangular outline SECONDA...

Страница 9: ...ERATING positions Inserting the crank in the center hole and turning to the limit in the counter clockwise direction moves the pointer and racking bar from the connected OPERATING position out to the RACKED OUT position Turn ing the crank to the limit in the clockwise direction moves the pointer and the racking bar on the breaker into the connected position The maintenance handle is used to close ...

Страница 10: ...I w w w E l e c t r i c a l P a r t M a n u a l s c o m ...

Страница 11: ... the drawout handle back the breaker into the housing so that the guide bar on the breaker enters the guide slot in the housing Push breaker toward rear until breaker reaches the floor stop which latches it in the TEST position IO Fig 13 5HV 150 and 5HV 250 Racking and Indicator Assembly Unlock Position If it is desired to test the breaker for operation electrically and manually before putting it ...

Страница 12: ...w w w E l e c t r i c a l P a r t M a n u a l s c o m ...

Страница 13: ...ed OPERATING position Fig 18 REMOVING 5HV 150 AND 5HV 250 BREAKER FROM HOUSING 1 Trip breaker by means of the control switch on front of housing IB 5909 Fig 15 Manually Closing Circuit Breaker While in Test Position 2 Open door insert crank and rack breaker Fig 17 to RACKED OUT position as indicated by pointer on breaker nameplate If it is desired to remove the breaker completely from the housing ...

Страница 14: ...w w w E l e c t r i c a l P a r t M a n u a l s c o m ...

Страница 15: ...w w w E l e c t r i c a l P a r t M a n u a l s c o m ...

Страница 16: ...r fo Raclced Oul Position 1 t Fig 18 Circuit Brealcer in Fully Connected Position 12 Fig 17 Racking in Circuit Brealcer to Fully Conneded Position i Fig 19 Pu ling Out Circuit Breaker from Housing w w w E l e c t r i c a l P a r t M a n u a l s c o m ...

Страница 17: ...ease lever and rack the breaker to the OPERATING position as shown in Fig 21 IB 5909 Fig 21 Raclcing in SHV 350 Breaker to Fully Connected Position REMOVING 5HV 350 BREAKER FROM HOUSING 1 Trip the breaker by means of the control switch 2 Open the compartment door insert the rack ing rod push down on the racking release lever and rack the circuit breaker out to the rEST position as indicated by the...

Страница 18: ... J w w w E l e c t r i c a l P a r t M a n u a l s c o m ...

Страница 19: ...ave been placed in the test position Close all doors to the switchgear as a safety measure Those breakers necessary to energize the main bus should be moved to the connected position and closed Observe undervoltage relays or other devices that should function properly when the main bus is energized Next move each circuit breaker in turn to the connected position and close Method explained under IN...

Страница 20: ...w w w E l e c t r i c a l P a r t M a n u a l s c o m ...

Отзывы: