20
Installation
6. START UP AND ADJUSTMENT
1. Installation:
Install the equipment and connect the pumps (see Installing and Wiring)
2. Equipment calibration and configuration:
Calibrate the sensors (pH, flow meter, etc.) (see Calibration)
Configure the equipment:
- Setpoint
- Type of control
- Installation and equipment configurations
3. Check readings
Start up the installation and check that the sensor reading are correct
4. Check operation of the dosing pumps:
Use “Manual” activation if available
5. Determine “T delay” (time delay), according to the installation
6. Alarms:
Once proper operation of the installation has been confirmed, configure the alarms
See section 4.5
Содержание WTRTEC Green
Страница 1: ...WTRTEC ENGLISH...