8.1 Before switching on
1. Visually check the fire panel for any damage that might have occurred during
installation. In particular, check for loose pieces that could have fallen in the
electronics.
2. Check that all harnesses are securely plugged into the correct plug positions on the
printed circuit boards.
3. Ensure that both the mains switch and the battery on/off switch are in the OFF
position.
4. Enable the lithium battery by linking the jumper J5 (located above the battery on the
host CPU board) to the ON position.
5. Unlock the memory.
6. Set the panel to service mode (this prevents any output from switching during
commissioning).
7. Connect the main supply to the power supply input terminals or connect the 24 V to
the 24 V supply board.
8. Connect the batteries to the battery terminals of the power supply. Observe correct
polarity!
9. Connect the repeaters (Fireman’s panels) to the current loop terminals. For detail
refer to the FM800 Installation, Configuration and Detailed Operation Manual.
10. Connect the network card (if necessary) - for detail refer to the Network Configuration
Guide.
11. Ensure that the fire panel is well earthed at the earth terminals provided. The earth
must be directly wired to the distribution board earth. This is required for reasons of
both safety and interference suppression.
12. Ensure that all field devices are connected and that their addresses are correctly set.
"
Loop isolators must have the correct polarity wired.
13. Use a multimeter to check all field wiring for short circuits, continuity, and earth faults.
If isolators have been used in the loop wiring, then one wire of the loop will not have
continuity. Continuity, earth fault and short circuit must be checked between each
isolator.
CAUTION!
DO NOT MEGGER THE LOOPS - This will damage devices connected to
the loops.
14. Connect all field wiring to the fire panel. The service switch ON will prevent outputs
from switching.
15. Ensure that NO loose bare wiring exists in the fire panel cabinet. This can cause
damage to the electronics.