3.1 Mechanical Description and Adjustment
Working principle and structure:
1. The automatic bottle rinse machine applies rotary sprinkle inner and outer washing principle.
2. Machine main device: washing device, entry and exit bottle thumb-‐wheel and guide set, convey device.
The governor using electromagnetic motor, the power transmission device will spread to dial, dial
on the folder containing bottles of mechanical hand, mechanical hand with a rotary dial, the
bottle into the bottle in the role of the device into the bottle transferred to the district, the
manipulator will be transferred to the bottle Clamping so that the bottle into the washing area,
while the role of the rails under the auto-‐complete 180-‐degree flip, flushing, brown, etc. Washing
processes, and then reset by the bottle dial wheel, thus finished bottle washing process, reach the
purpose to wash, delivering to the filling machine by the transport chain.
Adjustment
Adjustment of wheel set:
Because of transportation, you must adjust the machine’s synchronization. Loose the screw bolt,
turn the thumb wheel clockwise or anti-‐clockwise until the bottle-‐block groove on the thumb
wheel in the correct position, then fasten the bolt.
Adjustment of cleaning parts:
Disassemble the above locking plate; put the handle into the hole and rotary the round nut as
clockwise. Then rinsing parts will rise. At last, fit on the locking plate.
Debugging
1. Connect the lower part of the pipeline and the row of the pipelines.
2. Electrical wiring must meet the plane on the subject of the direction of rotation; it prohibited
the wheel reverse operation.
3. Rinse the bottles by the high plane, using the wrench to rotation spindle adjustment place highly
suitable for the position, at the same time, in front of the folder bottles Cam transferred to the
robot opened moderately.
4. Connected to the main electrical switch, rotating the speed control, make the appropriate
speed, to see whether the whole machine is smooth, if it is normal operation, you can put the
bottle to test machine.
5. If producing the different diameter bottle must be replaced with the suitable dial wheel and the
arc plank, and at the same must adjust the distance between the two baffles until match with the
bottle diameter.
Operation
1. Preparation before turn on the machine.
2. Check if all the oil-‐inject parts have been injected.
2.1 Turn on the power to check if the machine operates well. Also you need to check the supplied
and drain water pipes and if there is a stoppage in rinsing pipes.
2.2 Stop immediately when bottles are damaged, and remove the trouble at once.