IMC IMCQS Series Скачать руководство пользователя страница 4

 

   

4   

1.3

 

Installation   

   

v

 

Only   a   qualified   technician   should   perform   the   machine   installation   or   a   suitably   trained   

person.   
Note:

   

it   is   dangerous   to   work   on   a   moving   machine   and   the   machine   should   be   off   and   isolated   

before   any   form   of   work   is   performed.   
   

 

Machine   should   be   placed   in   a   well-­‐ventilated   room,   free   from   dust   and   excessively   

corrosive   materials.   

 

There   should   be   at   least   1,5m   space   around   each   side   of   the   machine   for   convenient   

operation   and   maintenance.   

 

Prepare   the   power   supply   380V   or   220V/50HZ.   Three/Single   Phase   and   neutral,   and   

connect   to   an   appropriate   earth   wire.   

   

 

Pneumatic   connections   should   take   place   as   the   designated   connection.   The   air   should   

not   be   less   than   6Bar   while   the   machine   is   operational.   Air   should   be   free   of   water   and   
contaminants.   

 

The   machine   should   be   placed   on   level   ground.   After   installing   the   machine,   check   if   the   

machine   is   level   by   Level   Instrument.   If   not,   please   adjust   the   four   legs.   

 

Check   every   part   of   the   machine   carefully   for   damage   during   shipping.   Tighten   any   loose   

parts,   screws   and   moving   parts.   

 

All   gearboxes   should   be   checked   for   sufficient   oil.   

 

Check   all   electrical   connections   for   loose   wires.   

 

Make   a   test   of   the   machines   electrical   power   and   confirm   the   voltage   and   earth   

continuity.   All   safety   connections   relative   to   your   own   country   should   be   adhered   to.   

 

Before   operating   the   machine,   please   lubricate   the   following   parts:   across   sealing   bearing   

and   its   bearing   holes,   longitudinal   where   sealing   the   parts   needs   oil.   

   

1.4      Electrical   and   Pneumatic   connections   

This   machine   requires   only   a   single   phase   connection   and   earth   wire   

   

v

 

DISCLAIMER   

IMC   will   not   be   held   responsible   fir   incorrect   installation   and   subsequent   failure   of   the   
machine   due   to   any   installation   procedure   not   being   followed.   

   
   
   

Содержание IMCQS Series

Страница 1: ...1 IMCQS Series of Automatic Washing Machinery INTERNATIONAL MACHINE CONCEPTS WELCOMES YOU TO YOUR NEW MACHINE Operation Manual Date 2015 Version 1 Serial Number...

Страница 2: ...nnections 1 4 Chapter 2 Technical Parameters and Description 2 1 Chapter 3 Operation Instruction Mechanical description and adjustments 3 1 Chapter 4 Malfunctions Faults and their rectification Table...

Страница 3: ...ly break open the exterior panels to reveal the machine and its working parts The machine will be covered in a plastic protective cover This is to be removed Make sure that no parts have been damaged...

Страница 4: ...chine should be placed on level ground After installing the machine check if the machine is level by Level Instrument If not please adjust the four legs Check every part of the machine carefully for d...

Страница 5: ...uirement 0 75Kw Bottle Diameter 50 100mm Bottle Height 160 300mm Dimensions L1200 W1100 H1800mm Capacity 2000 3000 bottle hour Productivity of 2L bottles 1000b h Bottle Damage rate 3 Washing heads 12...

Страница 6: ...the bolt Adjustment of cleaning parts Disassemble the above locking plate put the handle into the hole and rotary the round nut as clockwise Then rinsing parts will rise At last fit on the locking pla...

Страница 7: ...oosen the five screws of the thumb wheel and guide plate Remove the top guide plate Loosen the three columns in the guide plate Remove the bottom guide plate and then install in order Remove the origi...

Страница 8: ...s height 1 2 Loosen the screws adjust the height and then tight it Screw the screw on the bottom of the big gear when clockwise the filling cylinder will move down when counter clockwise the filling c...

Страница 9: ...system check drive unit for fault if in fault disconnect power from machine and wait 5 minutes and then switch on machine again If problem persists main drive unit may be damaged Replace unit Water se...

Страница 10: ...peration parts regularly Lubrication of each part 1 Lubrication of gears 2 Lubrication of bottle clamping in washing machine 3 Lubrication of gear box Check whether with lubrication oil or not every w...

Страница 11: ...loosen in some part when checking all is ok can start the machine 2 After working should clean the machine and note to add oil in moving part 3 Check the electricity box for making sure it is dry 4 G...

Страница 12: ...12 Chapter 6 6 1 Electrical Diagrams Pinboard No 1 2 3 4 5 6 7 Connect line name Phase line Mid line F1 F2 U1 V1 W1 AC220V power...

Отзывы: