9
Installation and Servicing
Section 1 - General
The Boiler has been tested and certified to:
BSEN 15502-1, BSEN 15502-2, BSEN 15502-2-1,
BSEN 60335-1, BSEN 60335-2-102, BSEN 55014-1 and
BSEN55014-2 for use with Natural Gas & Propane.
Detailed recommendations are contained in the following
British Standard Codes of Practice:
BS5440:1
Flues (for gas appliances of rated input not
exceeding 70 kW).
BS5440:2
Ventilation (for gas appliances of rated input
not exceeding 70 kW).
BSEN12828
Heating Systems in buildings: Design for water
based heating systems.
BSEN12831
Heating Systems in buildings: Method for
calculation of the design heat load.
BSEN14336
Heating Systems in buildings: Installation
and commissioning of water based heating
systems.
BS5546
Installation of gas hot water supplies for
domestic purposes (2nd Family Gases)
BS6798
Installation of gas fired hot water boilers of
rated input not exceeding 70 kW.
BS6891
Installation and maintenance of low pressure
gas installation pipework.
BS 7593:2019
Code of practice for the preparation,
commissioning and maintenance of domestic
central heating and cooling water systems.
Health & Safety Document No. 635.
The Electricity at Work Regulations, 1989.
The manufacturer’s notes must NOT be taken, in any way, as
overriding statutory obligations.
IMPORTANT:
This appliance is UKCA/CE certificated for
safety and performance. Do not connect external control devices
directly to this appliance unless recommended in this manual or
by
Ideal Heating
in writing. If in doubt, please enquire.
Unapproved control devices could invalidate the warranty of this
appliance and infringe the Gas Safety Regulations.
1.6 SAFE HANDLING OF SUBSTANCES
No asbestos, mercury or CFCs are included in any part of the
boiler or its manufacture.
1.7 LOCATION OF BOILER
The boiler must be installed on a flat and vertical internal wall,
capable of adequately supporting the weight of the boiler and
any ancillary equipment.
The boiler may be fitted on a combustible wall and insulation
between the wall and the boiler is not necessary, unless
required by the local authority.
WARNING:
Rear access to the boiler is not permitted.
CAUTION:
Do not fit the boiler outside.
Timber Framed Buildings
Boilers installed in a timber-framed building must comply with
IGE/UP7 +A 2008.
Bathroom Installations
CAUTION:
This appliance is IP20 rated, do not clean
with jets of water.
You may install the boiler in any internal space. The installation
must comply with the current IEE (BS 7671) Wiring Regulations
and the electrical regulations applicable in Scotland.
If the appliance is to be installed in a room containing a bath or
shower then, the appliance must be installed beyond Zone 2,
as detailed in BS7671.
Compartment Installations
A boiler installed in a compartment does not require
ventilation. However, A boiler installed in a compartment must
provide adequate clearances for servicing.
The compartment should also be fitted with a suitable label in
accordance with current standards.
Refer to Section
1.14
Bathroom Installations
[0] Zone 0
[1] Zone 1
[2] Zone 2
[2*] Without the end wall, zone 2 must extend 600 mm from the bath