14
British Gas 40 - 80 RD2 -
Installation & Servicing
INSTALLATION
FLUE KITS
Pack B:
supplied as standard.
Pack D:
optional extension kit for side
flue, top or rear flue outlet. Refer to 'Flue
Extension Ducts'
1.
A maximum of 3 extension ducts (plus
the standard flue duct) may be used
together.
2.
Flue extensions of greater than 1m
(39") should be supported with the
bracket provided.
It is MOST IMPORTANT that the boiler is installed in a vertical position.
11 DETERMINING THE FLUE LENGTH
10 BOILER CASING REMOVAL - continued
6.
Release the screw securing the control box to the
baseplate and slide to the left to release the box.
7.
Remove the 2 screws securing the top panel to the
sides.
8.
Draw the top panel forward and lift it off the boiler.
9.
Remove the 2 screws securing the LH side panel to
the turret front panel and baseplate.
10.
Pull the panel forward, disengaging from the
collector hood tab, lift it clear of the locating peg
and remove.
11.
Repeat steps 9 and 10 to remove the RH panel.
12.
The boiler is held to the packaging base by 4 M6
hex head screws. Remove the front screws,
slacken the rear screws and remove the boiler from
the packaging base.
WARNING.
For top outlet installation the flue
terminal MUST always be in the
horizontal position.
Top outlet flue length
= A + B + Elbow allowance
90
o
Elbow = 1m
45
o
Elbow = 0.7m
Flue length mm
Pack Requirement
Product No.
Up to 600
B, 1 off
150 308
600 to 1550
B, 1 off + D, 1 off
150 308+152132
1550 to 2500
B, 1 off + D, 2 off
150 308+
152132, 2 off
2500 to 3000
B, 1 off + D, 3 off
150 308+
152132, 3 off
INST
ALLA
TION