Device Installation and Commissioning
2.1
Gateway GW3 Commissioning
Insert the micro USB plug from the power supply into gateway GW3 and connect the power plug
to the power supply (wait about 30 sec.).
2.2
Sensor Commissioning
2.2.1
Sensor Activation
The sensor must be activated with the supplied magnetic button before first use. To do this, stroke
the magnetic button over the sensor at the marked point (see pictures below).
WLT-20 Sensor
WLRHT and WLRT Sensor
2.2.2
Sensor Placement
Then place the sensor in the cooling unit or at the desired location. The distance between the
gateway and the sensor should not exceed 3m and the two units must be in the same room.
Mikro USB Stecker
Mikro USB
Anschluss
Netzstecker