Specifications subject to change without notice.

The electrical ground and polarity for 115--v wiring must be
properly maintained. Refer to Fig. 32 for field wiring information

and to Fig. 72 for furnace wiring information.

NOTE

: If the polarity is not correct, the STATUS LED on the

control will flash rapidly and prevent the furnace from heating. The
control system also requires an earth ground for proper operation
of the control and flame--sensing electrode.
The 24--v circuit contains an automotive--type, 3--amp. fuse located
on the control. See Fig. 36. Any shorts of the 24--v wiring during

installation, service, or maintenance will cause this fuse to blow. If

fuse replacement is required, use ONLY a 3--amp. fuse. The control
LED will display status code 24 when fuse needs to be replaced.

Troubleshooting

Refer to the service label. See Fig. 65.
The Troubleshooting Guide can be a useful tool in isolating
furnace operation problems. Beginning with the word “Start,”

answer each question and follow the appropriate arrow to the next
item. See Fig. 71
The Guide will help to identify the problem or failed component.
After replacing any component, verify correct operation sequence.
Proper instrumentation is required to service electrical controls.

The control in this furnace is equipped with a Status Code LED
(Light--Emitting Diode) to aid in installation, servicing, and

troubleshooting. Status codes can be viewed at the indicator in
blower door.

The amber furnace control LED is either ON

continuously, rapid flashing, or a code composed of 2 digits. The

first digit is the number of short flashes, the second digit is the
number of long flashes.
For an explanation of status codes, refer to service label located on
control door or Fig. 65, and the troubleshooting guide which can

be obtained from your distributor.

Retrieving Stored Fault Codes

NOTE

: Fault codes cannot be retrieved if a thermostat signal

(24-V on W, Y, G, etc.) is present, or if any delays such as blower
off-delays are active.
The stored status codes will NOT be erased from the control
memory when 115- or 24-v power is interrupted. See the Service

Label (Fig. 65) for more information. The most recent fault code

may be retrieved as follows:

1. Leave 115-v power connected to furnace.

2. Observe the status LED through the blower door (the lower

door on upflow applications) indicator. Refer to the Service
Label (Fig. 65) to interpret the LED.

3. Remove the Main/Control door (the upper door on upflow

installations).

4. BRIEFLY disconnect and reconnect ONE of the main limit

wires.

5. The LED will flash the last stored fault code. Refer to the

Service Label (Fig. 65) to interpret the LED.

6. A component test sequence will follow.

7. Reinstall the Main/Control door.

Component Self-Test

NOTE

:

The furnace control component test allows all

components to run for a short time; except the gas valve and
humidifier terminal HUM are not energized. The EAC-1 terminal
is energized when the blower is energized. This feature helps
diagnose a system problem in case of a component failure. The
component test feature will not operate if any thermostat signal is
present at the control and not until all time delays are completed.
To Begin Component Self-Test:

1. Remove blower access door.
2. Disconnect the thermostat R lead from furnace control.

3. Manually close blower door switch.

Caution must be taken when manually closing this switch for

service purposes.

ELECTRICAL SHOCK HAZARD

Failure to follow this warning could result in personal injury,

or death.
Blower door switch opens 115--v power to furnace control.

No component operation can occur unless switch is closed.

Exercise caution to avoid electrical shock from exposed

electrical components when manually closing this switch for

service purposes.

!

WARNING

4. For approximately 2 sec, short (jumper) the COM-24v

terminal on control to the TEST/TWIN 3/16—in. (5 mm)
quick-connect terminal on control until the LED goes off.

Remove jumper from terminals. See Fig. 36.

NOTE

: If TEST/TWIN and COM-24v terminals are jumpered

longer than 2 sec, LED will flash rapidly and ignore component
test request.
Component test sequence is as follows:

j. Inducer motor starts and continues to run until Step g of

component test sequence.

k. After 7 sec the hot surface ignitor is energized for 15 sec.,

then off.

l. Blower motor operates on Continuous-FAN speed for 10

sec.

m. Blower motor operates on HEAT speed for 10 sec.

n. Blower motor operates on COOL speed for 10 sec.

o. Inducer motor stops.

5. Reconnect R lead to furnace control, remove tape from

blower door switch, and re-install blower door.

6. Verify furnace shut down by lowering thermostat setting

below room temperature.

7. Verify that furnace restarts by raising thermostat setting

above room temperature.

Checklist

1. Put away tools and instruments. Clean up debris.
2. Verify that the jumper is removed from the TEST/TWIN

terminal. Verify that there is nothing plugged into the PLT
connector. (Note: If there is a jumper connector plugged

into PLT, remove it and discard.) See Fig. 36.

3. Verify that the Blower/Heat Off Delay jumpers are set as

desired. See Fig. 36.

4. Verify that there are no unsealed openings in the blower

shelf or casing.

5. Verify that the blower and control (“Main”) doors are

properly installed.

6. Verify that the Status LED glows. If not, check that the

power supply is energized and that the blower door is
secure. See Fig. 65.

7. Cycle test furnace with room thermostat to be sure that it

operates properly with the room thermostat. Check all

modes including Heat, Cool and Fan.

8. Check operation of accessories per manufacturer’s

instructions.

9. Review Owner’s Manual with owner.

10. Attach entire literature packet to furnace.

Содержание R92ESN

Страница 1: ...g Portions of the text and tables are reprinted from current edition of NFPA 54 ANSI Z223 1 with permission of National Fire Protection Association Quincy MA 02269 and American Gas Association Washing...

Страница 2: ...grade directly in line with the exhaust vent terminal for the horizontally vented gas fueled heating appliance or equipment The sign shall read in print size no less than one half 1 2 inch in size GAS...

Страница 3: ...12 17 1 2 445 15 7 8 403 16 406 8 3 4 222 122 5 55 6 0601412 14 3 16 361 12 1 2 319 12 9 16 322 7 1 8 181 122 0 55 3 0601714 17 1 2 445 15 7 8 403 16 406 8 3 4 222 132 0 59 9 0801716 17 1 2 445 15 7 8...

Страница 4: ...e on tags and on labels attached to or shipped with furnace and other safety precautions that may apply These instructions cover minimum requirements and conform to existing national standards and saf...

Страница 5: ...n be converted in the field for use with propane gas when a factory supplied conversion kit is used Refer to the furnace rating plate for conversion kit information These furnaces are not approved for...

Страница 6: ...400 N Capitol N W Washington DC 20001 FIRE INJURY OR DEATH HAZARD Failure to follow this warning could result in personal injury death and or property damage When the furnace is installed in a residen...

Страница 7: ...th minimum fire protection clearances shown in Table 1 or on the furnace clearance to combustible construction label PERSONAL INJURY AND OR PROPERTY DAMAGE HAZARD Improper use or installation of this...

Страница 8: ...cate with the outdoor to provide sufficient air for combustion The combustion air pipe cannot be terminated in attics or crawlspaces that use ventilation fans designed to operate during the heating se...

Страница 9: ...000 divided by 3 000 33 3 Sq In for each Single Duct or Opening 80 000 30 000 110 000 divided by 2 000 55 0 Sq In for each two Horizontal Ducts Table 4 Minimum Space Volumes for 100 Combustion Ventil...

Страница 10: ...equired volume for the space Table 4 Minimum Space Volumes were determined by using the following equations from the current edition of the National Fuel Gas Code ANSI Z223 1 NFPA 54 9 3 2 2 1 For oth...

Страница 11: ...sate Drain section for information how to install the condensate drain A11307 Fig 8 Upflow Trap Configuration Appearance may vary Condensate Trap Downflow Orientation When the furnace is installed in...

Страница 12: ...begin the trap conversion S Refer to Condensate Drain section for information how to install the condensate drain Condensate Trap Horizontal Orientation When the furnace is installed in the horizonta...

Страница 13: ...Allowed The field supplied accessory horizontal drain trap grommet is ONLY REQUIRED FOR DIRECT VENT APPLICATIONS It it NOT required for applications using single pipe or ventilated combustion air ven...

Страница 14: ...ensate trap is inside the furnace casing The condensate drain must be routed from the trap through the furnace casing The condensate drain can be routed through the left or right side of the casing Th...

Страница 15: ...o temporarily rest on the blower shelf upflow or burner box downflow NOTE When the inducer housing has been removed to ease installation in upflow applications this step is not needed 7 After insertin...

Страница 16: ...N coil is used with a 060 14 furnace the N coil must either be raised using a transition piece at least 3 in 76 mm high or if a transition piece is not used the refrigerant lines of the N coil must p...

Страница 17: ...e panel installed in bottom return air opening This panel MUST be in place when only side return air is used Where required by code seal bottom closure to furnace with tape mastic or other durable sea...

Страница 18: ...ver connect return air ducts to the back of the furnace WARNING MINOR PROPERTY HAZARD Failure to follow this caution may result in minor property damage Local codes may require a drain pan under entir...

Страница 19: ...8 600 Downflow Applications on Combustible Flooring with coil assembly coil or coil box Subbase not required 19 483 19 483 20 508 20 508 24 1 2 622 Upflow Applications on Combustible or Noncombustibl...

Страница 20: ...3 34 0 21 52 0 32 81 1200 566 0 08 20 0 17 43 0 27 68 16x 25 Filter Factory Accy Washable Representative After Market Filter Media Fiberglass Pleated CFM L s 1 in 2 5 cm 1 in 2 5 cm 2 in 5 cm 1 in 2 5...

Страница 21: ...OTTOM RETURN 14 3 16 360 16 x 25 x 3 4 406 x 635 x 19 14 x 25 x 3 4 356 x 635 x 19 Washable 17 1 2 445 16 x 25 x 3 4 406 x 635 x 19 16 x 25 x 3 4 406 x 635 x 19 Washable 21 533 16 x 25 x 3 4 406 x 635...

Страница 22: ...g Fig 26 Working Platform for Attic Installation 2 IN 51 mm COMBUSTION AIR PIPE SEE VENTING SECTION Install 12 x 22 204 x 559 mm sheet metal in front of and above the burner compartment area The sheet...

Страница 23: ...oll out shield AIR DUCTS Many states provinces and localities are considering or have implemented standards and or restrictions on duct sizing practices ductwork leakage and or ductwork thermal airflo...

Страница 24: ...650 1595 1545 Yellow Alt Cooling or alt Heating 1650 1590 1535 1475 1425 1370 1315 1260 1205 1145 Blue Heating or alt Cooling 1495 1430 1365 1310 1260 1200 1145 1085 1030 970 Orange Alt Cooling or alt...

Страница 25: ...29 Gas Entry 1 1 2 inch for Gas 7 8 inch for 115 VAC Electric A170125 Fig 30 Alternate Gas and Electric Entry NOTE Top plate may be field drilled for alternate gas and 115 VAC electric entry Refer to...

Страница 26: ...prevent air leakage Remove the knockout install the grommet in the knockout then insert the gas pipe The grommet is included in the loose parts bag See Fig 29 ELECTRICAL CONNECTIONS ELECTRICAL SHOCK F...

Страница 27: ...load amps Time delay type is recommended Length shown is as measured one way along wire path between furnace and service panel for maximum 2 percent voltage drop ELECTRICAL SHOCK AND FIRE HAZARD Fail...

Страница 28: ...ctions must be located inside the external electrical box Do not leave splice connections unprotected inside the furnace The J Box cover mounting bracket and screws are shipped in the loose parts bag...

Страница 29: ...wer leads as shown in Fig 32 7 Attach furnace J Box cover to mounting bracket with screws supplied in loose parts bag Do not pinch wires be tween cover and bracket See Fig 34 BX Cable Installation in...

Страница 30: ...0 01 6201 00B Specifications subject to change without notice A190023 Fig 36 Example of Single Stage Furnace Control A11157 Fig 37 Field supplied Isolation Relay for Humidifiers with Internal Power Su...

Страница 31: ...nting system manufacturer s installation instructions for the polypropylene venting system installation NOTE When using polypropylene venting systems all venting materials used including the vent term...

Страница 32: ...standard Canadien CAN CSA B149 est directement reli l installation conforme aux instructions ci haut mentionn es Le standard Canadien recommande l inspection par un personel qualifi et ce une fois pa...

Страница 33: ...ve moisture entering the combustion air inlet pipe a moisture trap may be added to the inlet pipe to help prevent moisture from entering the furnace from the combustion air inlet pipe See Fig 50 When...

Страница 34: ...Table 12 Vent Termination Kit for Direct Vent 2 pipe Systems Vent and Combustion Air Pipe Diameters Approved Two Pipe Termination Fittings Allowable Concentric Vent Kit 1 1 2 in 38 mm 2 in 51 mm 2 1...

Страница 35: ...ield supplied brackets or supports fastened to the structure NOTICE When determining appropriate location for termination consider the following guidelines 1 Comply with all clearance requirements sta...

Страница 36: ...in 305 mm Permitted only if veranda porch deck or balcony is fully open on a minimum of two sides beneath the floor See Note 4 Manufacturer s Recommendation See Notes 3 8 M Clearance to each side of...

Страница 37: ...under a veranda porch deck or balcony 12 in 305 mm Permitted only if veranda porch deck or balcony is fully open on a minimum of two sides beneath the floor See Note 4 Manufacturer s Recommendation S...

Страница 38: ...305 mm Vertical clearance to a soffitt located above the vent termination within a horizontal distance of 2 ft 61 cm from the centerline of the vent termination 6 ft 2 M Clearance to a ventilation ex...

Страница 39: ...stance to the property line of the adjacent lot no type of vent termination is permitted for appliances with inputs greater than 35 000 btuh There are no additional restrictions on unobstructed distan...

Страница 40: ...on air inlet pipe a moisture trap may be added to the inlet pipe to help prevent moisture from entering the furnace from the combustion air inlet pipe See Fig 50 When sizing venting systems the equiva...

Страница 41: ...nnections The tee may also be connected to the intake air pipe on the side of the casing See Fig 50 In any configuration it will be necessary to add the equivalent length of the tee 15 feet 5 M to the...

Страница 42: ...t Length MEVL shown for that application for that specific furnace input size Compare the Total Equivalent Vent Length TEVL to the MEVL 8 If the Total Equivalent Vent Length is shorter than the Maximu...

Страница 43: ...tlet Restrictor disk P N 337683 401 1 25 in 32 mm Dia shipped in the loose parts bag or available through Replacement Components required under 10 ft 3 M TEVL in all orientations Required for installa...

Страница 44: ...warm hu mid spaces 6 Install the insulation per the insulation manufacturer s in stallation instructions NOTE Pipe length ft M specified for maximum pipe lengths located in unconditioned spaces canno...

Страница 45: ...her unused knockout may be used for combustion air connection UPFLOW VERTICAL VENT A11310A Fig 53 Upflow Configurations Appearance may vary See Notes for Venting Options 1 2 3 4 5 6 7 5 Rotate vent el...

Страница 46: ...Vent Kit See Product Data for Current Kit Number HORIZONTAL RIGHT LEFT VENT CONFIGURATION A11336 ALTERNATE COMBUSTION AIR CONNECTIONS HORIZONTAL RIGHT RIGHT VENT CONFIGURATION A11335 Fig 56 Horizontal...

Страница 47: ...nter Design Temp C Unit Size 40 000 BTUH 60 000 BTUH Uninsulated 3 8 in Insulation 1 2 in Insulation Uninsulated 3 8 in Insulation 1 2 in Insulation Pipe Dia mm 38 51 64 38 51 64 38 51 64 38 51 64 76...

Страница 48: ...ter by the absence of an internal pipe stopping ring The vent pipe can pass through the vent pipe adapter it cannot pass through the inlet pipe adapter 2 Align the screw holes in the plastic vent pipe...

Страница 49: ...18 Complete the vent and combustion air pipe installation by connecting the concentric vent or by installing the required termination elbows as shown in Figs 39 40 and 49 For Ventilated Combustion Ai...

Страница 50: ...dewall for vent and when used combustion air pipes Sidewall holes for two pipe vent terminations should be side by side allowing space between the pipes for the elbows to fit on the pipes Holes in the...

Страница 51: ...kits are ULC S636 listed CANADA 1 Installation in Canada must conform to the requirements of CAN CSA B149 code 2 Vent systems must be composed of pipe fittings cements and primers from the same suppli...

Страница 52: ...es Maximum Equivalent Vent Length MEVL 95 ft 29 M For 2 pipe from Table 13 Is TEVL less than MEVL YES Therefore 2 pipe MAY be used Example 2 A direct vent 60 000 BTUH furnace installed at 2100 ft 640M...

Страница 53: ...rgized whenever blower operates HUM 24vac terminal is only energized when the gas valve is energized in heating Prime Condensate Trap with Water CARBON MONOXIDE POISONING HAZARD Failure to follow thes...

Страница 54: ...ressures in Table 20 adjust for BOTH altitude and natural gas heating value Table 18 Altitude Derate Multiplier for U S A ALTITUDE PERCENT OF DERATE DERATE MULTIPLIER FACTOR FT M 0 2000 0 610 0 1 00 2...

Страница 55: ...r similar device to manifold pressure tap e Turn gas valve ON OFF switch to ON f Manually close blower door switch g Jumper R and W thermostat connections on control to start furnace See Fig 36 h Remo...

Страница 56: ...ature rise S Decrease blower speed to increase temperature rise ELECTRICAL OPERATION HAZARD Failure to follow this warning could result in personal injury or death Disconnect 115vac electrical power b...

Страница 57: ...ning properly and that the limit will operate if there is a restricted return air supply or motor failure If the limit control does not function during this test the cause must be determined and corre...

Страница 58: ...3 2 42 3 3 42 3 4 915 825 43 3 6 43 3 7 43 3 8 42 3 2 850 44 3 8 43 3 5 43 3 6 43 3 7 875 44 3 6 44 3 7 43 3 4 43 3 5 4000 900 44 3 4 44 3 5 44 3 7 44 3 8 1219 925 44 3 2 44 3 4 44 3 5 44 3 6 950 44 3...

Страница 59: ...3 4 2134 700 43 3 5 43 3 7 43 3 8 42 3 2 725 44 3 8 43 3 4 43 3 5 43 3 6 750 44 3 5 44 3 7 44 3 8 43 3 4 8000 775 44 3 3 44 3 4 44 3 5 44 3 7 2438 800 44 3 1 44 3 2 44 3 3 44 3 4 825 44 2 9 44 3 0 44...

Страница 60: ...60 440 01 6201 00B Specifications subject to change without notice A190036 Fig 65 Service Label Information...

Страница 61: ...ion Remove and recycle all components or materials i e oil refrigerant control board etc before unit final disposal CAUTION ELECTRICAL OPERATION HAZARD Failure to follow this caution may result in imp...

Страница 62: ...Self Test NOTE The furnace control component test allows all components to run for a short time except the gas valve and humidifier terminal HUM are not energized The EAC 1 terminal is energized when...

Страница 63: ...t system before each heating sea son for water leakage sagging pipes or broken fittings Have vent pipes vent system serviced by a qualified service agency 6 Inspect any accessories attached to the fur...

Страница 64: ...7f Ensure wheel is positioned for proper rotation 9 Torque motor mounting bolts to 40 10 lb in when re assembling 10 Torque blower wheel set screw to 160 20 lb in when reassembling 11 Verify that blo...

Страница 65: ...pport the burner assembly and remove the screws that at tach the burner assembly to the heat exchanger cell panel 14 Remove wires from both rollout switches 15 Slide one piece burner out of slots on s...

Страница 66: ...there is no tension on the ignitor itself See Fig 67 8 Turn on gas and electrical supplies to furnace 9 Verify ignitor operation by initiating control board self test feature or by cycling thermostat...

Страница 67: ...ified service technician Primary Heat Exchangers If the heat exchangers get an accumulation of light dirt or dust on the inside they may be cleaned by the following procedure NOTE If the heat exchange...

Страница 68: ...period of time when temperatures will reach 32_F 0_C or lower unless winterized Follow these procedures to winterize your furnace UNIT COMPONENT DAMAGE HAZARD Failure to follow this caution may resul...

Страница 69: ...es out LED will flash the status code of the previous fault or status code 11 1 short and 1 long flash if there was no previous fault After the control repeats the code 4 times the control will go thr...

Страница 70: ...70 440 01 6201 00B Specifications subject to change without notice A190093 Fig 71 Troubleshooting Guide...

Страница 71: ...ergized Simultaneously the electronic air cleaner terminal EAC 1 is energized and remains energized as long as the blower motor BLWM is energized f Blower Off Delay When the thermostat is satisfied th...

Страница 72: ...72 440 01 6201 00B Specifications subject to change without notice A190036 Fig 72 Wiring Diagram...

Страница 73: ...ur installing dealer or classified section of your local telephone directory under Heating Equipment or Air Conditioning Contractors and Systems headings for dealer listing by brand name or contact In...

Страница 74: ...74 440 01 6201 00B Specifications subject to change without notice Copyright 2019 International Comfort Products Lewisburg TN 37091 USA...

Отзывы: